ADMINISTRATIVE COMMITTEE |
||||
|
||||
2. |
RECOMMEND FUNDING
PLAN FOR PURE WATER MONTEREY ADVANCED WATER PURIFICATION ELECTRICAL
FACILITIES |
|||
|
||||
Meeting Date: |
April 14, 2020 |
Budgeted: |
N/A |
|
|
||||
From: |
David J. Stoldt |
Program/ |
|
|
|
General Manager |
Line Item
No.: |
N/A |
|
|
||||
Prepared By: |
David J. Stoldt |
Cost Estimate: |
See Below |
|
|
||||
General Counsel Approval: N/A |
||||
Committee Recommendation: The Administrative Committee reviewed this item on April 14, 2020 and recommended _____________________. |
||||
CEQA
Compliance: Covered by Pure Water
Monterey certified FEIR. |
||||
SUMMARY: At its February 5, 2020 meeting the Water Supply Planning
Committee recommended to the Board a
proposed funding plan for the new Medium Voltage (MV) Switchgear, to be
adjusted for the actual bid received, with District portion not to exceed
$700,000 and then the item would go to the Districts Administrative Committee
and Board at their March 2020 meetings, utilizing the actual bid numbers. The bid opening was delayed to April 2, 2020
hence this is the first Administrative Committee meeting since bid opening.
Two bids were received, and the lowest bid was $2.4
million by Anderson Pacific. That is
approximately 60% higher than anticipated.
Reasons for the difference include over-specification of equipment and
supplier limitations under the Covid-19 pandemic. Under the proposed funding plan, the District
would be responsible for $1,249,800 almost 80% more than authorized by the
Water Supply Planning Committee. As a
result, it is staff recommendation to defer action on this item until Monterey
One Water (M1W) has an opportunity to consider its options.
RECOMMENDATION: The Committee should defer action on this
item until Monterey One Water (M1W) has an opportunity to consider its options.
BACKGROUND: In October 2016
the Monterey One Water (M1W) Board approved an Energy Supply Option Analysis
for the Advanced Water Purification Facilities (AWPF.) Based on the results of
that analysis, the AWPF will be served by both PG&E and the biogas
electrical generation plant at the Monterey Regional Waste Management District
(MRWMD).
In August 2018, MRWMD
informed M1W that they were not ready to expand the co-generation system and
the proposed PG&E Meter and Switchgear would not be able to be constructed
as part of MRWMDs current PG&E application. The designers worked with MRWMD and M1W staff
to come up with an alternative approach to provide power from MRWMD to the AWPF
without the need to change the existing PG&E Meter and Switchgear.
The power supply for the
AWPF Project is envisioned to come from two sources:
1. PG&E
Power. Medium voltage (21kV) power from a new
PG&E primary service connection to the AWPF (AWPF MV Switchgear). This is
the initial power for the AWPF to meet the program schedule for producing
purified water.
2. MPRWD-to-AWPF
Power. Medium voltage (21kV) power from the adjacent
MPRWD co-generation facilities. A new MPRWD MV Switchgear would deliver
cogeneration power to both PG&E and to the AWPF. The MPRWD-to-AWPF power
would be delivered over MPRWD-owned power lines.
Option 2, which is the
preferred long-term permanent solution, was originally estimated to cost
approximately $1.5 million. Construction
will be after facility operations begin, the Anderson Pacific AWPF construction
contract is closed out, and the State Revolving Fund (SRF) loan is finalized
and closed. Hence, the cost of the MV
Switchgear is likely to be an unreimbursed construction period cost.
Amendment 3 of the MPWMD-M1W
Cost Sharing Agreement says:
1.(d) Unreimbursed
Construction Period Costs Defined
From March 1, 2017 through
December 31, 2020, there may occur project related costs that are not allowed
to be capitalized to the project and paid or reimbursed by State Revolving Fund
Loans. Examples of those costs include, among others:
1.
Public Outreach
2.
Geochemical Water Quality
Modeling
3.
Groundwater Basin Modeling
4.
Facility Expansion Design
and Engineering
5.
Regulatory Proceedings
6.
Expansion Environmental
Scoping and Review
7.
Expansion Permitting
1.(e) Financing of GWR Unreimbursed Construction
Period Costs
MPWMD shall pay seventy-five percent (75%) of such
costs, and M1W shall pay twenty-five percent (25%) of such costs.
Because of the magnitude of
the cost, M1W and the District have agreed to seek contributions from two other
parties, Marina Coast Water District and MRWMD.
Based on the pre-bid estimate, a funding plan was proposed as follows:
$1,500,000 total cost
$ 208,500 Marina Coast Water District (13.9%
allocation)
$ 400,000 MRWMD
$ 668,250 District (75% of remainder)
$ 222,875 M1W (25% of remainder)
A summary of the timelines
for the PG&E Power and the MPRWD-to-AWPF Power for the AWPF Project are
provided below:
AWPF Power and MPRWD-to-AWPF Power Timeline
·
MPRWD submitted service
change application to PG&E Generation/Interconnection Group 2015.
·
M1W submitted application
for AWPF MV service to PG&E Service Planning Group Nov. 2016 along with
60% design drawings.
·
Discussed MPRWD-to-AWPF
power concepts with PG&E Service Planning Group March 2017.
·
Completed AWPF MV Switchgear
design. Bid with overall AWPF project May 2017. Submitted final AWPF MV
service design drawings to PG&E.
·
Completed 90% MPRWD-to-AWPF
Design submitted to MPRWD for Review Sept. 2017
·
Completed 100% MPRWD-to-AWPF
Design submitted to MPRWD for Review Jan. 2018
·
Discussed MPRWD-to-AWPF
power concepts with PG&E Service Planning Group Feb 2018. Was told to
contact the Generation/Interconnection Group for this coordination.
·
Received preliminary
PG&E Service drawings for the AWPF MV Switchgear in March 2018. Met with
PG&E at AWPF site.
·
MPRWD communicated with
PG&E Generation/Interconnection Group about the MPRWD- to-AWPF power
concepts August 2018. Was told to contact the PG&E Service Planning Group
for this coordination.
·
MPRWD requested a meeting
with both PG&E Generation/Interconnection Group and Service Planning Groups
to correct mis-understandings and conflicting
information from PG&E regarding consultation and approval for the MPRWD-to-AWPF
power supply August 2018.
·
AWPF Power: PG&E Conduit
installed to AWPF MV Switchgear location. Installed switchgear in Sep 2018.
·
Requested PG&E install
meter and power conductors in October 2018.
·
PG&E Power available late
2018.
·
Authorized re-design of new MPRWD
MV switchgear based on MPRWD and PG&E comments to the MPRWD-to-AWPF Design
in 2019. Unable to include revisions in
AWPF contract with Anderson Pacific.
EXHIBIT
None
U:\staff\Board_Committees\Admin\2020\20200414\02\Item-2.docx