ADMINISTRATIVE COMMITTEE |
||||
|
||||
4. |
RECOMMEND THE
BOARD CONSIDER AN INCREASE IN THE BUDGET FOR APPRAISAL SERVICES FOR MEASURE J
PHASE 2 ACTIVITIES |
|||
|
||||
Meeting Date: |
June 9, 2020 |
Budgeted: |
N/A |
|
|
||||
From: |
David J. Stoldt |
Program/ |
|
|
|
General Manager |
Line Item
No.: |
N/A |
|
|
||||
Prepared By: |
David J. Stoldt |
Cost Estimate: |
$126,000 w/contingency |
|
|
||||
General Counsel Approval: N/A |
||||
Committee Recommendation: The Administrative Committee reviewed this item on June 9 and recommended _____________________. |
||||
CEQA
Compliance: Not a project under CEQA. |
||||
SUMMARY: At the November 18, 2019 Board meeting additional areas of
consulting work were identified that would help best position the Board to vote
on a Resolution of Public Necessity sometime in 2020. Such activities, which are presently ongoing
include: Formal
Appraisal and Rate Study, Findings and Other Legal Work,
Operations Plan, and CEQA Work.
At
its December 16, 2019 meeting the Board approved an overall budget for the
scope of services totaling $1,241,000.
At this time, the District has received a proposal for MAI real estate
appraisal services to work jointly with Raftelis, the
consultants performing the formal valuation.
However, the overall approved budget would not be exceeded (see
BACKGROUND, below.)
The
appraiser, Chris Carneghi MAI, has estimated the
budget to be up to $120,000 because of the large number of properties and the
overall complexity. Mr. Carneghi has done this type of highly specialized work
before and has experience providing expert testimony in eminent domain legal
cases. His proposal is attached as Exhibit
4-A with sensitive information
related to real property negotiation removed.
RECOMMENDATION: Administrative Committee should consider a recommendation
to the Board to increase the budget for appraisal services for Measure J phase
2 activities to $120,000 and set aside an additional 5% contingency.
BACKGROUND: The overall budget approved by the Board in
December 2019 is shown in the table at the top of the next page. The CEQA consultant fee proposal came in far
less than budgeted, therefore this proposed change to the MAI Appraiser allows
the overall budget to remain $246,650 less than the overall approved budget.
Budget Summary
Item |
Consultant |
Approved Budget |
Current Budget |
Appraisal & Rate Study |
Raftelis MAI Appraiser |
$200,000 $35,000 |
$200,000 $120,000 |
Findings & Other Legal |
Rutan & Tucker |
$225,000 |
$225,000 |
Operations Plan |
Close & Associates Jacobs Engineering |
$145,000 $87,000 |
$145,000 $87,000 |
CEQA Work |
Rincon Consultants |
$450,000 |
$130,000 |
Other |
|
$40,000 |
$40,000 |
Contingency (5%) |
|
$59,000 |
$47,350 |
TOTAL |
|
$1,241,000 |
$994,350 |
EXHIBIT
4-A Proposal of Chris Carneghi
MAI
U:\staff\Board_Committees\Admin\2020\20200609\04\Item-4.docx