ADMINISTRATIVE
COMMITTEE |
||||
|
||||
9. |
MONTHLY PROGRESS REPORT – SANTA MARGARITA WATER TREATMENT
FACILITY. |
|||
|
||||
Meeting Date: |
September 15, 2020 |
Budgeted: |
N/A |
|
|
||||
From: |
David J. Stoldt |
Program/ |
N/A |
|
|
General Manager |
Line Item: |
|
|
|
||||
Prepared By: |
Maureen Hamilton |
Cost Estimate:
|
N/A
|
|
|
|
|
|
|
General Counsel
Review: N/A |
||||
Committee
Recommendation: The Administrative Committee
reviewed this item on September 15, 2020. |
||||
CEQA
Compliance: This action does not
constitute a project as defined by the California Environmental Quality Act
Guidelines Section 15378. |
||||
SUMMARY: This progress report is provided for information only, no action is required.
Work conducted after the previous progress report:
· Completed all underground process piping
· Completed 16” and 20” above-ground manifolds.
· Installed all control valves and flow meters.
· Completed blow-off piping
· Successfully pressure tested the new pipe
· Successfully passed bacteria testing of new pipe
· Completed southern 30” tie-in
· Completed northern 30” tie-in
· Moved bulk tanks into bays
· Began plastering the building
· Ninety-seven submittals have been received; ninety-five of those submittals have been closed.
No new change orders were issued.
A Notice of Delay was issued for the door hinges which are on the critical path. The contract substantial completion date will be updated when the effect of the delay can be quantified. Alternatives to minimize the delay effect are being implemented.
EXPENDITURES:
Base Contract: $4,649,400.00
Change Orders: $ 69,785.20 (1.50%)[1]
Total: $4,719,185.20
Paid: $1,630,836.57
(35%)[2]
EXHIBITS
None
U:\staff\Board_Committees\Admin\2020\20200915\09\Item-9.docx