MONTHLY PROGRESS REPORT – SANTA MARGARITA WATER TREATMENT
FACILITY |
|||
|
||||
Meeting Date: |
January 13, 2021 |
Budgeted: |
N/A |
|
|
||||
From: |
David J. Stoldt |
Program/ |
N/A |
|
|
General Manager |
Line Item: |
|
|
|
||||
Prepared By: |
Maureen Hamilton |
Cost Estimate: |
N/A |
|
|
||||
General Counsel Review: N/A |
||||
Committee
Recommendation: N/A |
||||
CEQA Compliance: This action does not constitute a project as
defined by the California Environmental Quality Act Guidelines Section 15378. |
||||
SUMMARY: This progress report is provided for information only; no action is required.
The final invoice was received for the Santa Margarita Water Treatment Facility construction contract. The following table details the construction contract cost:
Item |
Amount |
Notes |
Awarded Construction Contract |
$4,649,400.00 |
|
Allowed Contingency |
$464,940.00 |
10% of awarded construction contract amount |
Total Board Authorized Expenditure |
$5,114,340.00 |
|
Change Orders |
$190,968.42 |
4% of awarded construction contract amount |
Bid Items not Required |
-$160,000.00 |
Soundwall,
standby time |
Construction Contract Expenditure |
$4,680,368.42 |
|
Reimbursement Request |
-$112,551.43 |
Flow meter installed on behalf of Cal Am |
Estimated MPWMD Construction Contract Expenditure |
$4,567,816.99 |
The bid line item for soundwalls was a placeholder in the amount of $150,000 because the design was not finalized at bid time. As the design progressed, it became apparent that there is insufficient space for a soundwall, protective bollards, vehicle passage, and the temporary chlorination facility housing. A soundwall may be revisited as part of a future project. No standby time was used for the project, resulting in a $10,000 savings.
Cal-Am was required to install a flow meter (Meter Works) on the lateral pipeline connecting the Santa Margarita site to the transmission pipeline CalAm shares with Marina Coast Water District. MPWMD and Cal-Am agreed to install the meter as part of the Santa Margarita construction project in an effort to reduce cost and minimize public nuisance due to traffic impacts. A separate bid line item was created for the reimbursable Meter Works. MPWMD is submitting a reimbursement request to Cal-Am now that the construction contract final payment request has been received.