Recommendation: The Administrative Committee reviewed this item on
June 14, 2021 and recommended _______________. |
||||
CEQA
Compliance: This action does not constitute a project as
defined by the California Environmental Quality Act Guidelines section 15378. |
||||
SUMMARY: Staff proposes to use Monterey Bay
Analytical Services (MBAS) to complete water quality analysis in support of the
Seaside Groundwater Basin Watermaster. The District currently has a business relationship with MBAS and
is billed on a net 30 following completion of laboratory analysis.
RECOMMENDATION: The Administrative Committee should
recommend that the Board authorize the General Manager to spend up to
$10,000 to complete laboratory analysis related to the Watermaster in
FY 2021-2022.
BACKGROUND: The District has provided water quality
monitoring and data management support to the Seaside Watermaster to
meet the requirements outlined in the Seaside Groundwater Basin Monitoring and
Management Plan. The Plan is a requirement outlined in the 2007 Adjudication
Decision. The Monitoring and Management plan was adopted by the
Monterey County Superior Court in 2008 and outlines a series of monitor and
production wells to be sampled each water year. In the past the District has a contracted with the Watermaster to
carry out this work on their behalf. Should the Watermaster
choose to contract with the District again, District
staff will use MBAS to complete the laboratory analysis for the sampling
required in the Plan.