ADMINISTRATIVE
COMMITTEE |
||||
|
||||
3. |
CONSIDER
EXPENDITURE OF FUNDS FOR CONSULTANT SERVICES FOR UPGRADES AT THE SLEEPY
HOLLOW STEELHEAD REARING FACILITY |
|||
|
||||
Meeting Date: |
July
12, 2021 |
Budgeted: |
Yes |
|
|
||||
From: |
David J. Stoldt, General Manager |
Program/ |
Protect
Environmental Quality
|
|
|
|
Line Item
No.: |
2-3-1-O |
|
|
||||
Prepared By: |
Larry
Hampson and Thomas Christensen |
Cost
Estimate: |
$
to be provided |
|
|
||||
General
Counsel Review: N/A |
||||
Committee
Recommendation: The Administrative
Committee reviewed this item on July 12, 2021 and
recommended ____________. |
||||
CEQA Compliance: Exempt
under §15262. |
||||
SUMMARY: Staff proposes to retain a consultant to
assist with preparation of plans, specifications, a cost estimate, and bid
documents for completing maintenance work to the Sleepy Hollow Steelhead
Rearing Facility. Although recent
upgrades were completed to improve the reliability and quality of the water
supply for the facility, other portions of the facility including the rearing
channel liner and quarantine tanks have reached their end-of-life cycles and are in need of maintenance and upgrades.
Staff requested proposals from four consulting
firms, but only two expressed interest or had the necessary expertise. As of the date for submittal of staff notes,
no proposals had been received; however, staff expected to have proposals for
Administrative Committee review on July 12.
RECOMMENDATION: The Administrative Committee should recommend
that the Board authorize the General Manager to enter into an agreement with
________ for consultant services in an amount not-to-exceed $__________ and approve
a contingency of $________ for additional consultant work.
DISCUSSION: The Sleepy Hollow Steelhead Rearing Facility
was constructed in 1996 and was intended at the time to be a short-term
mitigation activity for impacts to steelhead from diverting Carmel River flows
until a new water supply was built. Recent
upgrades to the facility were designed to improve the reliability and quality
of the water supply. However, the
upgrade did not address other components at the facility that have reached or
exceeded their life expectancy.
Staff proposes to carry out replacement of
portions of the Hypalon liner used to prevent water from leaking out of the
rearing channel. The liner, which has a
life expectancy of less than 20 years, has deteriorated, leaks in several
areas, and needs replacement.[1]
While the entire liner should eventually be
replaced, staff is proposing to replace only the liner in 16 of the 17 pools in
the rearing channel (one pool liner was recently replaced). Cobbles originally installed in the pools in
1996 to mimic natural habitat have been removed, which simplifies the removal
of the existing liner and reinstallation of a new liner. Work to replace this portion of the liner
would be carried out in the winter of 2021-22.
Staff may replace the liner in the remainder of the channel as a
separate project in the future.
In addition to the channel work proposed
for the upcoming winter, five fiberglass tanks used for quarantine purposes are
cracked and/or the bases supporting the tanks are deteriorating. These would be replaced and refrigeration
units for the tanks would be removed and replaced. The existing chillers are more than 20 years
old and chiller technology has advanced significantly since the original
installation. New chiller technology
includes the use of variable-speed drives, an evolution in control hardware, software,
and sensors that have led to improvements in industrial chiller reliability, accuracy and energy efficiency. Staff is also considering centralization
of refrigeration into one unit that can
quickly cool individual tanks or be used to cool specific portions of the
rearing channel when water temperatures are too high.
Project construction work, which will be
subject to future bid processes, consists of:
Rearing channel pool maintenance (16
total):
Remove
existing Hypalon liner in each pool
Excavate
and dispose on site of approximately 6 inches of native material under the pools
Shape
pool to drain
Pour
steel reinforced waterproof concrete slab (e.g., add Xypex to the concrete mix);
integrate into existing rearing channel concrete walls; work would require
inspection for rebar and concrete testing (minimum 4,000 psi concrete)
Install
new liner and integrate existing liner with new pool configuration at upstream
and downstream edges of the pool
Repair
top boards on rearing channel walls (if required)
Fill
rearing channel and inspect for water leakage
The plan set would include a site plan,
typical sections, and details of the rearing channel pool and rebar configuration. Specifications would include concrete
strength, rebar size, concrete additives, and liner specifications. There may
be a need for a shoring design for the existing walls during excavation and
concrete pouring. Approximately 6 inches
of material will be removed from under the existing pool walls, which are 18
inches thick at the base and 10 inches thick at the top. Symmetrical pools may not require shoring;
however, non-symmetrical pools may need temporary supports across the tops of
the pool.
Quarantine Tanks (5 total)
Remove
and salvage decking
Cut
plumbing (air, water, drain); disconnect electrical service and monitoring cables
Remove
and dispose existing quarantine tanks
Remove
existing chillers and replace with individual chillers or a centralized unit capable of lowering water temperature up to
approximately 10 degrees (TBD through calculation)
Excavate
and dispose native material under the existing tanks (depth TBD)
Determine
adequacy of native fill and import, compact, and test new base material as required
Pour
steel reinforced, waterproof concrete slab
Build
new steel or aluminum support frames and reset tanks; connect plumbing, air,
electrical, drains, and monitoring cables above the decking or in an easily
accessible critter-proof box
Reinstall
decking
Test
all components
Consultant services would include a site
inspection, a new set of plans and specifications, and preparation of a class 2
Opinion of Probable Construction Cost.
An issue at the facility to be addressed is how to reduce daytime
temperatures in the quarantine tanks, which can rise into a range that is
stressful or lethal to young steelhead.
To determine appropriate equipment for an upgrade of refrigeration
facilities, a site inspection and analysis of the existing power supply would
be performed. Additional services could
include assistance during future invitations for bids.
Staff requested proposals from three local
firms Whitson Engineering, the Wallace Group, and Harris and Associates and
from Tetra Tech, the firm that provided design and construction expertise for
the recently completed upgrade to the water supply. Whitson Engineering declined to propose
citing a lack of expertise for the requested services. The Wallace Group declined to propose and
stated that they would not be able to meet the schedule for the work. Harris and Associates and Tetra Tech stated
they are interested and would provide proposals.
Because of a potentially long lead time to
procure replacement tanks, MPWMD staff intend to prepare plans and
specifications as a separate project and invitation for bids. Approval for purchase of the tanks would come
before the Board of Directors for consideration at a future meeting, possibly
early in the fall of 2021. Similarly,
approval for construction of the project would also come before the Board of
Directors at a future meeting possibly in January of 2022.
IMPACTS ON STAFF AND RESOURCES: Funds for this work are budgeted under Sleepy
Hollow Operations Budget Program line item 2-3-1-O Design/Construct Rearing
Channel and Quarantine Tank Improvements.
The work would be performed under the direction of the District Engineer.
EXHIBITS
Consultant proposals (to be supplied)
U:\staff\Board_Committees\Admin\2021\20210712\03\Item-3.docx
[1] Hypalon was a chlorosulfonated polyethylene (CSPE) synthetic rubber (CSM) noted for its resistance to chemicals, temperature extremes, and ultraviolet light. It was a product of DuPont Performance Elastomers. Production was discontinued in 2009. Burning Hypalon releases highly toxic fumes that are considered environmental pollutants. Additionally, Hypalon contains additives made from lead or lead compounds known for their danger.