ADMINISTRATIVE
COMMITTEE |
||||
|
||||
5. |
CONSIDER RECOMMENDING
AUTHORIZATION OF EXPENDITURE OF FUNDS NOT TO EXCEED $230,000 FOR ADDITIONAL
APPRAISAL AND COST OF SERVICE ANALYSIS BY RAFTELIS RELATED TO THE ACQUISITION
OF THE MONTEREY WATER SYSTEM (MEASURE J) |
|||
|
||||
Meeting Date: |
September 13, 2021
|
Budgeted: |
No |
|
|
||||
From: |
David J. Stoldt, |
Program/ |
Services & Supplies |
|
|
General Manager |
Line Item No.: |
Professional Fees |
|
|
||||
Prepared By: |
David J. Stoldt |
Cost Estimate: |
$230,000 |
|
|
||||
General Counsel Review: N/A |
||||
Committee Recommendation: The Administrative Committee reviewed this item on September 13, 2021 and recommended ____________________. |
||||
CEQA Compliance: This action does not constitute a project as
defined by the California Environmental Quality Act Guidelines Section 15378. |
||||
SUMMARY: Raftelis
has been the District’s financial consultant working on the acquisition of the
California American Water Company (Cal-Am) Monterey Water System since January
2019. In November 2019 the firm
completed the Preliminary Valuation and Cost of Service Analysis Report
determining that an acquisition of the System is financially feasible. Raftelis provided additional work on rate
impacts and formal appraisal work that was ready to go in October 2020. Unfortunately, delays in the LAFCO process
have resulted the appraisal work becoming “stale” and in need of updating. Additional cost of service analysis and rate
impact analysis will likely also be needed to inform the District Board’s
decision to move forward. There is $14,440 remaining in their budget and July
and August invoices have not been reflected.
Raftelis scope of services (redacted) is attached as Exhibit 5-A. The
proposed budget is just under $230,000.
RECOMMENDATION: The Administrative Committee should recommend that the Board authorize expenditure of funds not to exceed $230,000 for additional appraisal and cost of service analysis by Raftelis related to the acquisition of the Monterey Water System (Measure J).
IMPACT TO DISTRICT RESOURCES: Such
Measure J related expenses have not been budgeted and will come from District
reserves.
EXHIBIT
5-A Raftelis Proposed Scope of Services and Budget
U:\staff\Board_Committees\Admin\2021\20210913\05\Item-5.docx