ADMINISTRATIVE
COMMITTEE |
||||
|
||||
2. |
Consider Approval of Funds and a Contract for the Sleepy Hollow
Steelhead Rearing Facility Quarantine Tanks Replacement Project |
|||
|
||||
|
||||
Meeting Date: |
March
14, 2022 |
Budgeted: |
Yes |
|
|
||||
From: |
David J. Stoldt, General Manager |
Program/ |
Protect
Environmental Quality
|
|
|
|
Line
Item
No.: |
2-3-1-O |
|
|
||||
Prepared By: |
Larry
Hampson |
Cost
Estimate: |
$ |
|
|
||||
General
Counsel Review: N/A |
||||
Committee
Recommendation: The Administrative
Committee reviewed this item on March 14, 2022, and
recommended ____________. |
||||
CEQA Compliance: Exempt under §15301 Existing Facilities. |
||||
SUMMARY: Staff proposes to contract for the replacement
of fiberglass reinforced tanks (FRP) and certain electrical components used in
operating the District’s Sleepy Hollow Steelhead Rearing Facility
(Facility). Bids
for the project were received from ___________.
The bid forms are attached as Exhibit 2-A
(to be provided at the meeting). The low bidder was ___________. The
engineer’s estimate for the project was $75,000 to $105,000.
RECOMMENDATION: The Administrative Committee should recommend
that the Board authorize the General Manager to enter into
a contract with ______________ for the work in an amount not-to-exceed $__________. Due to the unknowns associated with this
work, staff is requesting approval of a contingency amount of $________ (20% of
the contract amount) for unforeseen circumstances.
DISCUSSION: The Facility was initially constructed in 1996
and has been modified on several occasions, including 2018, when the District undertook a major upgrade of several of the
components necessary to successfully rear steelhead rescued from the Carmel
River. However, the FRP tanks and
associated plumbing and electrical equipment used to control disease in fish
rescued from the river were not replaced with the 2018 upgrade. The tanks and their support systems are in
various states of disrepair with cracks and failing foundation supports. The existing tanks also do not have insulated
covers, which leads to stress-inducing water temperatures. New tanks would include covers to minimize
heat gain during warm periods and new chillers capable of cooling the tanks to
the desired temperature (i.e., 55 to 60°F).
Bid advertisements were placed three times
with the Monterey County Weekly; the project was placed on ebidboard.com (a comprehensive
cross-agency database of California public works construction projects and
documents); and staff reached out via email to several contractors with
experience at the Facility. Bids for the
project were received from ___________ (see Exhibit 2-A – to be provided at
the meeting). The low bid by
__________ responded to all District requirements. __________ has approximately ______ years of experience
in contracting.
Much of the work involves removal of an
existing deck, plumbing, and electrical equipment under the deck and
reconnecting to existing infrastructure underground that has limited as-built
information. For this reason, staff is
asking for a 20% contingency for unforeseen conditions.
CEQA:
The
California Environmental Quality Act Section 15301 exempts maintenance of
existing facilities, including those under section i).
“ Maintenance of fish screens,
fish ladders, wildlife habitat areas, artificial wildlife waterway devices,
stream flows, springs and waterholes, and stream channels (clearing of debris)
to protect fish and wildlife resources; ”
The quarantine tanks are an integral part
of the rearing facility.
IMPACTS ON STAFF AND RESOURCES: Funds for this work are budgeted under Sleepy
Hollow Operations Budget Program line item 2-3-1-O Design/Construct Rearing
Channel and Quarantine Tank Improvements.
The work would be performed under the direction of the District Engineer.
EXHIBIT
2-A Bid Forms (to be provided at the meeting)
U:\staff\Board_Committees\Admin\2022\20220314\02\Item-2.docx