FINANCE AND ADMINISTRATION COMMITTEE |
|||||
|
|||||
ITEM: |
ACTION ITEM |
||||
|
|||||
2. |
CONSIDER AUTHORIZING THE GENERAL
MANAGER TO ENTER INTO A CONTRACT WITH MONTGOMERY AND ASSOCIATES TO PROVIDE A
TULARCITOS ASR FEASIBILITY STUDY |
||||
|
|||||
Meeting Date: |
March 13, 2023 |
Budgeted: |
Yes |
||
|
|||||
From: |
Dave Stoldt |
Program/ |
1-1-3, 1-7-1 |
||
|
General Manager |
Line Item No.: |
335-03-786038, 35-04-786016 |
||
|
|||||
Prepared By: |
Maureen Hamilton |
Cost Estimate: |
$119,200 |
||
|
|||||
General
Counsel Approval: N/A |
|||||
Committee
Recommendation: The Water Supply Planning Committee reviewed this item on March
6, 2023 and recommended approval on a 3-0 vote. The Finance and Administration Committee
reviewed this item on March 9, 2023 and recommended ______________. |
|||||
CEQA Compliance: This action does
not constitute a project as defined by the California Environmental Quality
Act Guidelines Section 15378. |
|||||
SUMMARY: MPWMD holds a suite of water right permits that originated with
the proposed New Los Padres Dam on the Carmel River. Water rights (WR) 20808 A
and C are used for ASR diversions to injection; WR 20808 B remains unused. A condition for maintaining WR 20808 B is
that the permittee (MPWMD) must demonstrate that a project is diligently
pursued.
A suite of potential
projects was identified and ranked by ability to utilize water under WR 20808
B. The Tularcitos ASR project (Project)
was selected for the first feasibility study (Feasibility Study). The Feasibility Study will determine the viability
of the Project to divert water from the Carmel River, inject it into ASR wells located
in the Tularcitos Creek subwatershed, and recover the water during dry periods.
Groundwater modeling provides
the basis of the proposed Feasibility Study.
The Feasibility Study
cost estimate is $119,200. Staff
proposes $80,000 be funded by budgeted Permit 20808 B Alternatives Analysis
program 1-7-1, and the remaining $39,200 be funded by the modeling budget
program 1-1-3.
Consultant work will be
conducted on a time and materials basis not to exceed $119,200.
RECOMMENDATION: The Finance and Administration Committee
should recommend that
the Board authorize the General Manager
to enter a contract with Montgomery and Associates to provide a Tularcitos ASR
Feasibility Study to the District for an amount not to exceed $119,200.
BACKGROUND: The
water right process has three phases: (a) application, (b) permit, and (c)
license. A permit is the legal authorization to divert water in accordance with
conditions and within a time frame, and to develop the project. When that time frame elapses, a permittee
should either:
(1) request revocation of the permit if the project
has been abandoned or cannot be diligently completed due to personal or
financial reasons;
(2) petition for an extension of time to extend the
development schedule if the construction and use of water under the permit has
been diligently pursued and additional time is necessary to complete full
anticipated beneficial use of water; or,
(3) notify the State Water Board that the permitted
project is complete and ready for licensing.
It is difficult to show
diligence in pursuing a new large dam on the Carmel River after 2003. However, the District could cite evidence
that a new large dam would not be permitted and show progress toward planning
for smaller projects, as was done for the existing ASR projects.
On April 20, 2020 the
Board directed District Staff to respond to an State Water Board letter that
MPWMD would file a Petition for Extension of Time to show beneficial use for WR
20808 B and withdraw the Petition for Extension of Time to construct New Los
Padres Dam. Once the District has
identified viable project(s), staff would file a Petition for Change to modify
the water right to apply to the new project(s).
Potential projects must
include facilities to extract water from the Carmel River, convey the water,
and store the water. Because conveyance
from the Carmel River to the Seaside Groundwater Basin is constrained and may
change, projects sited in the Carmel River watershed were prioritized.
The Project would divert
water from the Carmel River at the confluence with Tularcitos Creek at a
property owned by California American Water Company (Cal-Am). The water would
then be injected into and recovered from ASR wells screened in an unnamed
Miocene sandstone unit in the upland portions of the Tularcitos Creek
subwatershed that is bound by faults.
The Feasibility Study groundwater
modeling will simulate different project configurations using the Carmel River Basin
Hydrologic Model (Model) to evaluate ASR feasibility in the area of interest. Work
to complete the proposed Feasibility Study includes:
•
Analyzing the
availability of Carmel River water for ASR diversion
•
Developing a
hydrogeological framework and cross sections of the area of interest
•
Model-based evaluations
for ASR well feasibility and project sizing
•
Selecting hydrogeologic
units and sites for further analysis and field testing if preliminary screening
indicates potential project feasibility
Montgomery was founded
in 1984 and specializes in groundwater. Its
services include water supply, water recharge, water resource planning, groundwater
modeling, and water rights. Montgomery
maintains the Seaside Basin model for the Watermaster and Monterey One Water.
EXHIBIT
2-A Letter
Proposal from Montgomery and Associates to provide a Tularcitos ASR Feasibility
Study to the District