|
RULES & REGULATIONS REVIEW COMMITTEE |
|||||
|
||||||
1. |
CONSIDER CHANGES TO MPWMD
RULES & REGULATIONS GOVERNING WATER DISTRIBUTION SYSTEMS (Ordinances 96
and 105) |
|||||
|
||||||
Meeting
Date: |
August 2, 2004
|
Budgeted:
|
N/A
|
|||
|
||||||
From: |
David A.
Berger, |
Program/ |
N/A |
|||
|
General
Manager |
Line Item No.: |
||||
|
|
|
||||
Prepared
By: |
Henrietta
Stern |
Cost Estimate: |
N/A |
|||
General Counsel Approval: |
Staff note provided for review. |
|||||
Committee Recommendation: |
Rules & Regulations Review Committee expressedgeneral concurrence and recommended that __________________. |
|||||
CEQA Compliance: |
Needed to pursue new ordinance(s)
with substantive changes. |
|||||
NOTE TO
COMMITTEE: This item is
a continued discussion from the June 22, 2004 Rules & Regulations Review
Committee meeting. Two of three committee
members were present to review the materials and generally concurred with the
concepts presented. This staff note
reflects suggestions made by committee members on June 22 regarding text
refinements and presentation materials.
The following staff note is written for consideration by the full Board
at its August 16, 2004 meeting.
Additional refinements are planned based on discussions with the
Committee on August 2.
SUMMARY: The Board will consider recommendations by District
staff and the Board’s Rules & Regulations Review Committee regarding concepts for potential changes to MPWMD
Rules and Regulations governing water
distribution systems (WDS). The
District rules were substantively amended by Ordinances Nos. 96 and 105 in
2001-2002. The current goal is to
streamline the permit process, where appropriate, while continuing to protect
water resources. The California
Environmental Quality Act (CEQA) requirements for a new ordinance will also be
reviewed.
RECOMMENDATIONS: The Board should direct staff and counsel to
develop two ordinances for Board consideration in the near future. Two ordinances are recommended because it is
assumed that substantive changes to the permit process may take more than one
meeting and could hold up the housekeeping changes that are needed as soon as
possible. One ordinance is also an
option if preferred by the Board.
The first ordinance (“Ordinance XX”) would address
housekeeping/consistency issues that are needed regardless of changes to the
permit process. For example, this
ordinance would clarify the importance of production limits and what procedures
would occur if a WDS goes over its limit.
A first reading could be considered in September 2004.
The second ordinance (“Ordinance YY”) would reflect and codify the
multi-level, “impact-based” regulatory concepts presented herein, which would
be a substantive change to the procedures currently employed. The level of staff/Board review, documentation,
and permit fees would be proportional to the anticipated impact. Anticipated impact would be based on factors
such as intensity of water use, number of parcels, total acreage, and proximity
to sensitive environmental resources.
See the “Discussion” section below for more detail. A first reading could be considered as
early as October 2004.
At its June 22, 2004 meeting, the Rules & Regulations Review Committee concurred with the impact-based regulatory concept and recommended that two ordinances be developed. At its August 2, 2004 meeting, the Committee recommended that _________.
DISCUSSION:
Concepts for
Ordinance No. XX, Clarify WDS Rules and Regulations
Ordinance No. XX would focus on several
“housekeeping” topics, along with other text revisions needed to foster clarity. It is envisioned that Ordinance No.
XX would be exempt from CEQA. Ordinance
No. XX would address the following topics:
Ø Clarify importance of remaining within the production limit set as part of the permit conditions. For example, Rules 40-C and 40-D direct the Board to hold an annual public hearing to determine whether any system has exceeded its annual “expansion capacity limit” (connection limit), to notify the system owners, and for staff to deny any application for water in a system that has exceeded the connection limit. Rules 40-C and 40-D should be amended to also include the “system capacity limit” (production limit) to be consistent with Rules 40-A and 40-B. From a hydrologic impact perspective, compliance with the production limit is more important than compliance with the connection limit.
Ø Clarify what happens when a system goes over its limits, and describe options available (or required) to correct the situation. For example, the Rules and Regulations should state that the General Manager will direct staff to not receive or accept applications for water connection permits within systems that have exceeded their annual production or connection limits (measured from October 1 through September 30), and describe the documentation needed to demonstrate that system water use has fallen below the limit. Examples of documentation may include installation of new water–saving equipment estimated to substantively reduce annual water use; removal of sufficient turf/landscape acreage to substantively reduce water use; one year of production data showing reduced water production; revised rate schedules showing significant incentive to reduce water consumption; and/or other information as deemed acceptable by the General Manager.
Ø Clarify the importance of obtaining a WDS permit, if required, including characterization of the proposed water distribution system, enforcement and penalties for not obtaining a required permit. Currently, the emphasis is on revocation of a permit if conditions of approval are not carried out.
Ø Clarify 60-day deadlines for follow-up action (payment of fees, sign required paperwork) in order for a permit authorized by the Board or hearing officer to be signed and become valid. This would be in addition to the system construction and operation deadlines currently described in Rule 22-D-4.
Ø Clarify deadlines for responses to incomplete letters and other activity to show that a permit is actively in progress (due diligence). For example, an applicant may have up to six months to conduct hydrologic studies or provide other required by the District in an incomplete determination letter from the District.
Concepts for
Ordinance No. YY, Impact-Based Assessment of WDS
The Board
Chairperson asked staff to develop proposed modifications to current
regulations to streamline the WDS permit process and lessen financial impact to
property owners with less anticipated environmental impact, reduce unnecessary
staff effort, and continue to protect sensitive water resources and the
environment. The concept described in
the following paragraphs is termed an “impact-based” review of water
distribution systems. A new Ordinance
No. YY would codify the concepts described below. It is envisioned that a CEQA Initial Study/Negative Declaration
would be circulated for public review.
Staff recommends a new process whereby all owners of new wells permitted by the County (or other types of systems not based on wells), except for specific situations defined as exempt, submit an application form to MPWMD that briefly describes key characteristics of the property and proposed uses so that a rough estimate of water use and/or potential impact can be made. A preliminary mock-up of this worksheet is provided as Exhibit 1-A.
Based on this first screening, the application would be assigned as Exempt, Level 1, Level 2, Level 3, or Level 4 as shown in Exhibit 1-B. The level of regulation is proportional to anticipated impact based on the sensitivity of the geographic area, size of parcel, number of parcels served, and whether the application is residential or non-residential. In short, the five types of action include:
Ø
Exempt from
MPWMD Rule 20.
Ø
Level 1, Permit
Waiver – simplified permit issued but no system limits set.
Ø
Level 2, Staff
Permit – staff sets system limits and other conditions; no public hearing; can
be appealed to General Manager and Board.
Ø
Level 3, Public
Hearing – Staff hearing officer makes decision; can be appealed to Board.
Ø
Level 4, Public
Hearing – Board makes decision.
The five
types of action are described in more detail below.
Criteria to Determine Level
The determination of whether an application is Exempt or Level 1
through 4 will depend on the characteristics, or combination of
characteristics, of an application. The
characteristics are intended to give a general estimate of water use and
potential impact. These factors can
include:
Ø
Land Use
Type, such as single-family
residential, commercial or agricultural.
Ø
Number of
parcels/connections, that
is, how many parcels are served by the water system.
Ø
Size of lot, for example, larger lots are assumed to
have the potential for greater water use, especially in residential use. Due to the intensity of possible water in a
small space, lot size is not as an important factor in a commercial
setting. The lot acreages shown in Exhibit 1-B were selected to represent
potential water use as well as be consistent with other District regulations as
well as Monterey County regulations.
Ø
Geographic
area/location, such as
inside or outside the alluvial aquifer; based on environmental sensitivity of
the area, or similar compelling reason such as water rights, overdraft,
etc. The proximity of the proposed well
or other facility to existing wells, listed Carmel River tributaries, alluvial
aquifer boundaries or the shoreline is also important.
Ø
Relation to
Cal-Am, that is, whether or
not a property is inside or outside the Cal-Am service area, and is already
served by Cal-Am.
There is no distinction between a potable
(domestic drinking water) and non-potable (agricultural/irrigation only)
supply. The reason is that the quantity
of water being extracted out of the ground is the key factor in assessing
environmental effect, not how it may be treated and used by the property
owner. Also, a property owner on a
single parcel could initially apply for a non-potable well, ostensibly for
irrigation use only, and subsequently convert the well for potable use without
the knowledge of the County or District.
This scenario is of concern because, until SWRCB Order 95-10 is
resolved, the District does not wish to exempt situations where a private
potable system may fail, leading to a petition for Cal-Am service. For this reason, any supply (potable or
non-potable) proposed within the main Cal-Am service area begins at Level
2.
Characteristics of Action Levels
Following are proposed characteristics for each of the five action levels.
In the discussion below, the term “parcel” means an existing legal lot of
record (see Rule 11), and refers to a residential setting unless noted
otherwise. The term “subdivision” means
creation of new legal lots. For all
situations, the well must be properly registered and metered, and report
use annually.
The definition of “sensitive receptors” referenced below is based on the following:
Ø The 1,000-foot delineation for the zone of influence of a well drilled in Carmel Valley upland formations or other areas is based on extensive hydrogeologic studies associated with the Santa Lucia Preserve EIR certified by Monterey County in 1996. District staff members were part of a peer review team for these studies, which offer the best available information.
Ø The Carmel Valley Alluvial Aquifer (alluvium) is delineated due to the water rights determinations in SWRCB Order 95-10.
Ø The listed tributaries described in Rule 20 include: Tularcitos, Hitchcock Canyon, Garzas, Robinson Canyon and Potrero Creeks. These creeks were selected because: (1) they reflect the majority of contributed streamflow to the Carmel River in the lower Carmel Valley; (2) portions of each stream are mapped as part of the alluvial aquifer; (3) they are regularly monitored by MPWMD staff (including stream gauges); (4) extensive baseline data currently exist; and (5) data for these tributaries are included in the District’s CVSIM computer model; and/or (6) they are known to support habitat for sensitive species. Other smaller, intermittent tributaries are not recommended to be listed because it would be difficult to make environmental findings about them based on evidence in the record.
Ø The Pacific Ocean shoreline is included to address potential seawater intrusion that potentially could be caused by a well within l,000 feet of the mean high tide line, depending on the well.
Exemption/No Permit Needed:
Staff would continue to screen all Monterey County well construction permits sent to the District to assess whether an MPWMD WDS permit is needed. As shown in Exhibit 1-B, properties that meet all of the following criteria would be exempt from the requirement to obtain a WDS permit:
Ø one or two parcels totaling less than 2.5 acres;
Ø location outside of the Carmel River Basin and Seaside Basin (entire basin);
Ø location
not within the Cal-Am service area (or not served by Cal-Am as a remote meter);
Ø location
more than 1,000 feet from sensitive receptors defined above.
Only a very limited number of properties and situations would qualify as exempt. Examples include certain areas within the Carmel Highlands, Aguajito/Jack’s Peak, and Highway 68 uplands (not within Laguna Seca Subarea).
Level l, Permit Waiver
Level 1 properties are distinguished from exempt properties by being located in the upland areas of the Carmel River watershed as shown in Exhibit 1-B. A Permit Waiver would be issued with a basic set of assumptions that must hold true, or the waiver is invalid. No production or connection limits would be set. Characteristics for Level 1 include:
Ø one or two parcels totaling less than 2.5 acres;
Ø location
in Carmel Valley Upland more than 1,000 feet from sensitive receptors;
Ø location
not within the Cal-Am service area (or not served by Cal-Am as a remote meter).
Level 2, Staff Permit
Level 2 would be similar to the Corps of Engineers "Nationwide
Permit," where the process is streamlined for certain situations. There
would be no public hearing, but production and connection limits would be set,
along with other conditions, as determined by staff (General Manager or
designee). Additional information from the applicant, such as a
hydrogeologic study, and analysis by staff (or consultant, if needed) may be
required in certain situations, such as location of a well within 1,000 feet of
certain named creeks. Water rights are
not a key issue because Level 2 permits are for parcels outside the Carmel River
Alluvial Aquifer (see Exhibit 1-B).
Level
2 is the minimum level for situations within the main Cal-Am service area.
Level
3, Public Hearing before Staff Hearing Officer
Level 3 would entail formal notice and a public hearing before the MPWMD staff Hearing Officer, similar to the current situation. As shown in Exhibit 1-B, Level 3 situations reflect sensitive areas such as the Carmel River Alluvial Aquifer and Seaside Basin (Laguna Seca and Coastal Subareas); larger parcels in less sensitive areas; and systems serving three or more parcels. All new subdivisions and non-residential situations are Level 3 or 4.
Level
4, Public Hearing before MPWMD Board
Level 4 would entail formal notice and a public hearing before the MPWMD Board, similar to the current situation. As shown in Exhibit 1-B, hearings before the Board would be reserved for larger, potentially controversial projects, and/or wells located within known sensitive areas. All non-residential situations are Level 3 or 4. Subdivisions with total acreage greater than 2.5 acres are Level 4.
This proposed structure would expand the MPWMD “regulatory net” in sensitive areas, but streamline it in less sensitive areas or potentially lower impact situations. Staff believes this is a reasonable compromise to focus staff and Board attention on situations that require the most oversight and could cause the most impact to the community water resources. All boxes shown in gray in Exhibit 1-B are situations where the level of review is streamlined. All boxes shown in black are situations where the level of review is increased. Boxes in white are the same as the existing situation. Exhibit 1-C provides selected examples where the permit process would be decreased, increased or the same.
Expanded Regulation: The most prominent example of expanded regulation is the need for a Level 3 or 4 permit for single parcels within the Laguna Seca Subarea as well as the Coastal Subareas of the Seaside Basin. Previously, no WDS permit was needed for a single-parcel system in the Laguna Seca Subarea. This change reflects the findings of the Phase III Hydrogeologic Study for the Laguna Seca Subarea, which demonstrated that current water extractions are roughly double the reliable yield of the Subarea (overdraft condition), and that the Subarea is in a water supply deficit. Also, regulation of some single-parcel systems that are outside the Carmel River Basin and Seaside Basin Coastal Subareas, but still within the Cal-Am service would increase. For example, lots with wells in Pebble Beach would not be exempt.
Streamlined Regulation: An example of a more streamlined process (Level 1 or 2, depending on the situation) is that a public hearing would not be required for two-parcel systems outside of the alluvial aquifer. Currently, any two-parcel system would require a public hearing before the MPWMD Board. Under the proposed concept, staff would handle these applications administratively. Also, 3+ parcel situations less than 2.5 acres that currently require a public hearing before the Board would be heard by a staff hearing officer under the proposed refinements.
Pros and Cons of
Impact-Based System
The multi-level revisions described above were developed to address concerns about regulatory impact to the “small” property owner, increase efficiency, and continue to properly manage and protect sensitive water resources. Exhibit 1-D provides pros and cons of the impact-based permit system from the perspective of the Chair’s direction to streamline the permit process and reduce regulatory oversight for lower impact situations. It is acknowledged that the concept of “pro and con” may be a subjective assessment.
A sliding scale fee structure is proposed as follows, based on staff’s best estimate of actual time needed to process the permit, follow up on conditions, and track use annually. The staff hourly rate is $70 per hour; fees may be rounded for simplicity.
Ø Basic Application/Screening: $50 for review and determination of exemption or level.
Ø Exemption Confirmation: $50 for written Confirmation of Exemption.
Ø Level 1: $300 to review application, provide Permit Waiver with Conditions, track use.
Ø Level 2: $1,500 application fee, assuming 20 hours as base, plus County CEQA Exemption fee, etc. Charge at $70 per hour (over 20 hours) and all other expenses for more complex cases similar to Ordinance No. 106.
Ø Level 3 or 4: $2,500 application fee, assuming 35 staff hours as base. Charge $70 per hour for all time over 35 hours as well as actual legal and consultant costs (See Ord. 106).
Case law has determined that creation of an ordinance may be considered a “project” under CEQA. Previous Ordinances No. 96, 105 and 106 complied with CEQA via a Categorical Exemption or via a Negative Declaration. It is assumed that Ordinance No. XX would be exempt, and that Ordinance No. YY would require an Initial Study/Negative Declaration because there are adequate safeguards to protect environmentally sensitive areas.
BACKGROUND AND HISTORY:
Since the District was created in 1978, the District has adopted a series of
ordinances, beginning with Ordinance No. 1 in 1980, that created or amended
MPWMD Rules and Regulations that govern WDS within the District as well as
metering and registration of wells. Ordinances since 1980 are briefly
summarized below:
Ø Ordinance No. 3, adopted July 7, 1980. Enacted the MPWMD well registration and reporting requirements. Allowed well owners three options to report water usage: (1) land use method (parcels less than 2.5 acres only); (2) power consumption method; or (3) water meter method.
Ø
Ordinance
No. 48, adopted March 12, 1990. Deleted the power consumption method of reporting
for large wells, and required water meters for those wells.
Ø
Ordinance
No. 56, adopted November 25, 1991. Required that all medium,
large and new wells be measured and reported by the water meter method.
Ø Ordinance No. 96, adopted March 19, 2001. Expanded requirements for a permit to create a WDS. Single-parcel systems within the Carmel River Alluvial Aquifer, 1,000 feet from the alluvial aquifer and specific tributaries, and the Seaside Basin Coastal Subareas as well as some previously exempted multiple-parcel systems need a WDS permit.
Ø Ordinance No. 105, adopted December 16, 2002. Changed and refined Ordinance No. 96 requirements, including a WDS permit required for all wells within Carmel River Basin (watershed) located within the MPWMD boundary.
Ø Ordinance No. 106, adopted February 27, 2003. Revised fee structure to ensure that the WDS permit program is self-funded. Set a standard of $70 per hour for all MPWMD staff time.
In April 2001, the District Board approved draft
Implementation Guidelines, including a Supplement to the Guidelines, which
provide guidance on the water distribution system permit process, and include
worksheets, information sheets, an application form and other relevant
information. At its July 15, 2002 meeting, the Board authorized additional
refinements to the Guidelines recommended by staff.
Current
Status
Since
Ordinance No. 96 was adopted, staff has processed 10 permit applications; all
were eventually approved, with conditions that varied with the complexity of
the project. The approved permits
include eight single-parcel residential situations, one multiple-parcel (4 or
fewer lots), and one major subdivision.
Twenty requests for written Exemption Confirmation letters were also
completed, along with numerous phone consultations.
Currently,
there are 11 active pending applications, including single-parcel applications
(residential, agricultural and a church), multiple-parcel systems systems and
large subdivisions/housing developments.
Many inquiries regarding potential new applications are received each
week; intensified interest in recent weeks may be related to discussion of a
moratorium in the main Cal-Am water system.
Based on the
10 permits processed to date, the current permit process takes a minimum of
roughly 25 to 35 staff hours and 2 to 4 months between receipt of an
application and final approval.
Incomplete applications or more complex applications take longer.
The District well
registration program currently tracks water use for 49 permitted WDS as well as
many individual wells. In water year
2003 (October 1, 2002-September 30, 2003), there were 996 registered wells,
with 696 active and 257 inactive (and 43 unknown). Ninety-nine percent (99%) of the groundwater production within
the District was reported by the water meter method and 95% of registered well
owners reported their water production.
Currently, staff closely coordinates with Monterey
County Health Department, Division of Environmental Health (MCHD) regarding
issuance of new well construction permits by the County. All County permits for wells within the
District include a requirement to comply with MPWMD regulations for WDS; many
County permits specifically state that an MPWMD WDS permit must be obtained
before the County permit is valid.
IMPACT ON RESOURCES:
Implementation of Ordinances No. 96 and 105 has significantly increased
District staff workload because a full public hearing process is needed for
nearly all new well situations. Each
week, District staff consistently receives many requests for assistance
regarding WDS regulations from property owners, real estate agents and agency
staff. Each permit application processed to completion to date has taken
roughly 25-35 hours minimum of total staff time, more if complex hydrologic
issues are involved. A consultant has
assisted District staff on a regular basis since April 2003 in order to ensure
that the tight timelines associated with the State Permit Streamlining Act are
met. To date, the staff members most
affected by the water distribution system regulations are the Water Resources
Division Manager (registered hydrogeologist reviews technical data) and Project
Manager within the Planning and Engineering Division (permit processing and
CEQA review). The fee structure associated with Ordinance No. 106 has helped
enable the WDS permit program to be self-funding; staff recommends that the
existing fee structure be continued with the refinements noted above.
The impact-based system described above will take more staff time
initially to develop new rules, write implementation guidelines, train staff
and educate the public. However, once
in place, the impact-based system should result in less time spent with
lower-impact situations.
Staff has delayed revising the Implementation Guidelines until changes
to the Rules and Regulations are finalized.
A major effort is needed to create procedures manuals for staff as well
as worksheets and booklets for applicants, and put all relevant information on
the District website. Training of staff
in the Water Demand Division will be helpful, as many members of the public
first contact the District through that division. Expansion of the District website to include guidelines,
application forms and other information will help educate the public.
LIST OF EXHIBITS
1-A Preliminary information
sheet
1-B Proposed impact-based
review, with level of permit review
1-C Examples of whether
regulation increases, decreases or stays the same
1-D List of pros and cons to
impact-based system
U:\staff\word\committees\RulesRegsReview\20040802\01\item1.doc
Revised 7/28/04 per JO edits