RULES AND
REGULATIONS REVIEW COMMITTEE |
|||||
|
|||||
ITEM: |
ACTION
ITEMS |
||||
|
|||||
2. |
REVIEW AND DISCUSSION OF
MPWMD CONCEPT ORDINANCE -- ADD NEW RULE 23.6 TO ESTABLISH A WATER ENTITLEMENT
FOR SAND CITY AND AMENDING RULES 11, 21 AND 23.1 TO REFLECT THE PROCESS FOR
ISSUING WATER USE PERMITS |
||||
|
|||||
Meeting
Date: |
November 8, 2007
|
Budgeted:
|
N/A
|
||
|
|||||
From: |
David A.
Berger, |
Program/ |
N/A |
||
|
General
Manager |
Line Item No.: N/A |
|||
|
|||||
Prepared
By: |
Same |
Cost Estimate: |
N/A |
||
|
|||||
General Counsel Review:
Yes
|
|||||
CEQA Compliance: MPWMD is a Responsible Agency relying on FEIR
certified by City of |
|||||
SUMMARY: On
October 15, 2007 the Board of Directors considered and approved a Water
Distribution System (WDS) permit to allow the City of Sand City (City) to convey
water from its proposed 300 acre-feet/year (AFY) brackish water desalination
plant to the California American Water (CAW) water distribution system. The permit allows CAW to deliver this
desalinated water to existing customers within its
At its October 15 meeting the Board received, but did not directly address or consider, a MPWMD Concept Ordinance prepared by District counsel, which reflects policy choices based on a draft ordinance submitted by City’s legal counsel (Exhibit 2-A). The draft Concept Ordinance proposes to grant the City a legal entitlement to 206 AFY of the water produced by its desalination plant, and would create a District water use permitting process to authorize new CAW connections for parcels within the City to be served by its desalinated entitlement water. Special conditions in both the City and CAW WDS permits, which the Board approved on October 15, anticipate District adoption of such an ordinance. Specifically, the City’s permit authorizes a single connection to the CAW system; and approval of future CAW connections serving parcels located within the City limits is contingent upon creation by the ordinance of a 206 AFY “Desalination Water Entitlement,” provided the plant is completed, properly maintained and reliably able to produce 300 AFY of potable water under the CAW WDS permit. At the October 15 meeting, the Board referred the Concept Ordinance to the Rules and Regulations Review Committee without policy guidance, and directed that the Committee study and submit its recommendation regarding the ordinance to the Board for consideration. The purpose of this agenda item is for the Committee to review the Concept Ordinance submitted by the City, and to address the policy issues described in the Background section of this report.
RECOMMENDATION: District staff recommends that the Rules and Regulations Review Committee:
BACKGROUND: On October 15, 2007 the Board of
Directors considered and approved a WDS permit application submitted by the
City to enable delivery of potable water from the Sand City Water Supply
Project (Project), a desalination plant the City proposes to build and own that
would produce 300 AFY of potable water from shallow, brackish-water sources in
the
http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2007/20071015/20/item20.htm
Concept Ordinance Policy Issues
MPWMD General
Counsel Laredo’s memo of May 29, 2007 (Exhibit 2-B) suggested that an entitlement
ordinance be considered in connection with District action on the City and CAW WDS
permits, described above. District and
City attorneys coordinated on development of the draft Concept Ordinance, which
is known as the Sand City Water Supply Project Entitlement Ordinance (Exhibit 2-A). It proposes to create a new MPWMD Rule 23.6, and
would amend Rules 11, 21 and 23.1 to authorize issuance of District water use
permits from the City’s 206 AFY entitlement of potable CAW water to
The major
sections of the draft Concept Ordinance include:
A. Findings, Short Title and Purpose
B. Create new Rule 23.6 for Sand City Water
Entitlement
C. Amend Rule 21-E re: “Benefited
Properties”
D. Amend Rule 23.1 re: Water Use Permit for
a “Benefited Property”
E. Amend Rule 11 (Definitions) to be
consistent with entitlement, and add new definition for Sand City Desalination
Facility
A summary of
the key aspects of the draft ordinance include:
A. A Sand City Water Entitlement of 206 AFY
is created as a vested property right to the City as long as CAW takes delivery
of 300 AFY of potable water from the Desalination Facility. The City may then transfer the vested right
to individual properties within the City.
MPWMD will track how the 206 AFY “account” is “drawn down” over time.
B. The entitlement begins via a Water Use
Permit to the City when the Desalination Facility is fully operational; the
entitlement continues through December 2082.
C. The Entitlement is separate and distinct
from any other water allocation (Rule 30).
D. Properties within the City must abide by
all conservation and water rationing rules.
E. All standard fees associated with MPWMD
permits must be paid, as well as all charges imposed by the California Public
Utilities Commission (CPUC), CAW or other entities with authority.
F. MPWMD water factors apply to the
properties and MPWMD may track water use on these properties.
The content of the draft Concept Ordinance reflects substantive policy choices as presented by City Attorney Heisinger, though some minor text refinements were made by District General Counsel Laredo. In an October 1, 2007 memo Mr. Laredo identifies policy considerations not addressed in the draft Concept Ordinance submitted by the City Attorney (Exhibit 2-C). Since the Board provided no policy guidance to the Committee on the draft Concept Ordinance, and because they are not legal matters, District staff subsequently analyzed these policy issues. The purpose of this staff analysis was to determine differences and similarities between the policy purposes imbedded in Ordinances 39 and 109, and the physical and financial conditions inherent in the Sand City Water Supply Project, in order to suggest which of these policy issues are relevant and appropriate to address in any revision of the draft Concept Ordinance. This analysis is based on a thorough review of Ordinances 39 and 109 that authorized the original Carmel Area Wastewater District/Pebble Beach Community Services District (CAWD/PBCSD) Wastewater Reclamation and Expanded Recycled Water projects, respectively.
Staff found that neither Ordinances 39 nor 109 contain a recital or operative provision stating that their terms and conditions were intended as MPWMD policy precedent for other future water supply projects proposing an entitlement. To the contrary, these two ordinances very narrowly describe the terms and conditions related to the “fiscal sponsors” of the two sub-potable water supply projects, as well as the potable “water entitlement” granted to the Pebble Beach Company and two other Del Monte Forest property owners as a consequence of the projects’ effect in reducing potable water demand. Ordinances 39 and 109 were specifically tailored to the unique financial and physical conditions required to secure fiscal sponsorship of the two projects, and the water entitlement they created constituted the financial incentive needed to attract such fiscal sponsorship. These financial conditions do not exist in connection with the Sand City Water Supply Project, nor is there a need for the District to attract a financial sponsor for that project.
Specifically, Ordinance 39 was adopted to create a legal mechanism for fiscal sponsorship, and a financial guarantee of sufficient revenue required for repayment of District-issued debt financing, for the original reclamation project tertiary treatment and distribution system facilities constructed by CAWD and PBCSD, respectively. The 50 percent potable water entitlement limit in Ordinance 39 was intended to provide an adequate incentive to attract a guaranteed financial resource required for project capital cost debt amortization, and to cover any operations and maintenance (O&M) deficiencies resulting from inadequate revenues of recycled water sales. The primary purposes of Ordinance 109 were to: (1) amend Ordinance 39 to facilitate financing, construction and operation of the expanded reclamation (now called recycled water) project; and (2) allow a portion of Pebble Beach Company’s water entitlement to be sold to third parties within the Del Monte Forest in order to finance the expanded project, given its acknowledgment of the limited availability of public funds for such a purpose. District staff understands that the state awarded the City of Sand City a $2.9 million Prop. 50 grant for its desalination project, and the remainder of funds required to complete the design and construct the facility are available from financial resources controlled by the City and its redevelopment agency. MPWMD has no role in financing or attracting fiscal sponsorship of the project.
Based
on the foregoing analysis, staff finds that there are substantial factual
dissimilarities between the specific legislative purposes of Ordinances 39 and
109, and the District’s more limited legislative interest in the Sand City
Water Supply Project Concept Ordinance.
Thus, the rationale for including any of the policy issues raised by Mr.
Laredo should be based on the adequacy and clarity of the Concept Ordinance in
meeting physical conditions directly related to the District’s role in
regulating the
The summary
below simplifies Mr. Laredo’s October 1, 2007 memo, and poses a set of policy questions
that arise when he compared the draft Concept Ordinance to Ordinance No. 109,
or when other unaddressed issues are considered (shown in bold, italicized
text). Staff’s conclusions follow, shown in bold
text. The designation in brackets in
each paragraph below reflects numbering in General Counsel’s October 1 memo (Exhibit 2-C):
1.
[
Policy Question: Should language be added to the
ordinance to address the situation where production could be limited in order
to comply with the Adjudication decision?
This is also relevant to questions about long-term system failures (see
below).
Staff Conclusion: Include in ordinance;
this policy item directly relates to project source of supply that is addressed
in the
2.
[Memo IB] Ordinance 109 requires CAWD/PBCSD to maintain
public ownership and to keep the plant operational. Concept Ordinance Finding #6 refers to public
ownership but does not require the City to maintain public ownership of the
plant, or to keep it operational (see two additional questions related to this issue immediately below).
Policy Question: Should text be added to the
ordinance to require the City of
Staff
Conclusion: Include in ordinance for similar reasons as
stated in Item 1 above.
3.
[Memo
IB] The Ordinance 109 entitlement was granted pursuant to a guaranteed fiscal
sponsorship to ensure a viable reclamation project. The Concept Ordinance does not include a
requirement that the City guarantees or ensures that the plant is maintained in
good operating condition to be able to reliably produce 300 AFY. It is noted that Condition #3 and Special
Condition #28 of the approved MPWMD WDS permits for the City and CAW state that
the 206 AFY Entitlement is valid only so long as the plant is fully operational
and properly maintained to be able to produce 300 AFY of potable supply
acceptable to CAW.
Policy Question: Should language be added to the
ordinance to require a guaranteed fiscal sponsorship to ensure long-term
viability of the plant?
Staff Conclusion: Don’t include in
ordinance;
4.
[Memo
IB] Ordinance No. 109 specifies the definition of a service “interruption” and
what happens in a short-term or long-term failure of the reclamation project. It describes how long being off-line is
acceptable and the process to address system failure. The Concept Ordinance does not include any
information about short-term or longer-term system failure, including the situation
where less than 300 AFY is actually able to be produced over the long-term, for
whatever reason.
Policy Question: Should text be added to the
ordinance to address emergency short-term and long-term system failures,
including replacement sources of supply?
Staff Conclusion: Don’t
include in ordinance for similar reasons as stated above.
5.
[Memo
IC] Ordinance 109 allowed 380 AFY out of 800 AFY potential reclamation savings
to be used for new water use by the fiscal sponsor, or less than half. Concept Ordinance Finding #10 includes 206
AFY for new uses, which is about two-thirds of the 300 AFY production
amount.
Policy Question: Is the ratio of entitlement to
plant production acceptable?
Staff Conclusion: Don’t include in
ordinance; the 50% ratio in Ordinance 39 was needed to attract fiscal
sponsorship of CAWD/PBCSD project; there is no such requirement in this
instance as City is SCWSP fiscal sponsor using RDA, Prop. 50 and other
financing tools.
6. [Memo ID]
Concept Ordinance Finding #11 states that the Water Entitlement is
separate and distinct from the City’s Allocation and “won’t affect any future
Allocation to the City.”
Policy
Suggestion: The Board should confirm this separation.
Staff Conclusion: Include in
ordinance; this is a relevant and useful clarification.
7.
[Memo
IE] Ordinance 109 specified the cost of the Reclamation Project and who is
responsible for paying for it. The Concept
Ordinance does not include this type of information.
Policy
Question:
Should text be added to the ordinance to address project costs, cost of
water and who is responsible for payment (see specific questions in memo)?
Staff Conclusion: Don’t include in ordinance; see Item 5 rationale above.
8.
[Memo IF] Concept Ordinance Finding #18 notes near-term benefits to the
Policy Question: Should
text be added to the ordinance to clarify project benefits to the two primary
components of the CAW water resource?
Staff Conclusion: Don’t include in ordinance; clarification is unnecessary, based on facts described immediately above.
9.
[Memo
IG] Concept Ordinance Finding #18 refers to a “permanent reduction” of 94 AFY,
the City’s CAW water consumption in water year 2006. It is unclear how water currently used by the
City would be permanently reduced.
Policy
Question:
Should text for Finding #18 be amended to more accurately describe what
the 94 AFY amount represents?
Staff Conclusion: Include in ordinance; this is a factual
clarification, and the policy issue is directly related to the basis of the
proposed SCWSP water entitlement.
10.
[Memo
IIA] The purpose of the Concept Ordinance refers to resource benefits but does
not spell out potential benefits to the
Policy
Question:
Should text for Section Two, Purpose, be amended to emphasize benefits
to the
Staff
Conclusion: Include in ordinance; same as Item
9 rationale.
11.
[Memo
IIC] The
Policy
Question:
Should text for Section Two, Purpose, be amended to include limits on
the timing of the sale of entitlements to
Staff Conclusion: Don’t include in ordinance; Ordinance 109 financing source was unique to
the expanded recycled water project cost.
12.
[Memo
IIIA] The Concept Ordinance establishes a 75-year life for the entitlement
through December 21, 2082. This appears
to be inconsistent with a 25-year remaining life of the City’s Redevelopment
Plan described in other documents.
Long-term fiscal obligations by
Policy
Question: Should text in Section
Three, Rule 23.6, be amended to clarify the project life and financial
obligations during that period?
Staff Conclusion: Don’t include in ordinance; there is no policy correlation between RDA “life” and water entitlement duration; Ordinance 39 and 109 potable entitlements have no time limit, incidentally.
EXHIBITS
2-A MPWMD draft Concept Ordinance to
facilitate water entitlements to
2-B Letter from District
General Counsel dated May 29, 2007 regarding
2-C Memorandum from
District General Counsel dated October 1, 2007 regarding policy issues
associated with Concept Ordinance
U:\staff\word\committees\RulesRegsReview\2007\20071108\02\item2.doc