EXHIBIT 1-A
DRAFT MINUTES
Water Supply Planning Committee Meeting of the
Monterey Peninsula Water Management District
March 8, 2010
Call to Order
The meeting was called to order at 9:05 AM in the District conference room.
Committee members present: Bob Brower, Chair
Alvin Edwards
Kristi Markey (arrived at 9:15 AM)
Staff present: Darby Fuerst, General Manager
Comments from Public
No comments.
Action Items
1.
Receive
Minutes of February 2, 2010 Committee Meeting
On a motion
by Director Edwards and second by Director Brower, the minutes were received
unanimously on a vote of 2 – 0. Director
Markey was absent for the vote.
Discussion Items
2. Update
on Potential Water Projects Including Desalination
A. Staff Report on All Alternative Desal Sites and Feasibility
of Each Site Located Within the District Boundaries
The committee members reviewed the Work Plan and Schedule to Identify Project Sites, submitted by Andy Bell. The committee members agreed that if the District were to develop a desalination plant, the potential water supply goal should be 2,000 acre-feet. The committee agreed to continue to the next meeting, their discussion of feasibility criteria and results of a literature search.
3. Discuss
Next Steps re Development of 95-10 Desalination Project
Discussion and action are incorporated in item 2.A.
4. Review
Policy Regarding Cistern Use to Offset Outdoor Demand
The committee reviewed information provided by staff and agreed with the concept of offering water credits for installation of cisterns. The issue was referred to the Water Demand Committee for development of revised rules and a determination on issues such as enforcement, and if water from a cistern on one property could be used to irrigate a contiguous or non-contiguous lot.
During the public comment period on this item, John Bridges asked that the District develop rules that would encourage the use of cisterns to capture rainwater to provide a non-potable substitute water source for landscape irrigation, and that a water credit would be obtained to offset the amount of potable water that would not be used to irrigate landscaping.
5. Update
on Development of Recycled Wastewater Alternatives
The committee discussed the Monterey Regional Water Pollution Control Agency (MRWPCA) proposal to construct the Groundwater Replenishment Project as part of Phase II of the Regional Water Supply Project. Mr. Fuerst reported that the MRWPCA plans to refrain from taking any action on this project for six months. The committee also discussed the anticipated cost for the desalination project that is a component of the proposed Regional Water Supply Project. District Counsel was directed to provide at the May 15, 2010 Board meeting, an update on development of the reimbursement agreement between California American Water (Cal-Am), Marina Coast Water District and the Monterey County Water Resources Agency. When the agreement has been made public, staff should provide a presentation on the content at a future Board meeting.
6. Update
on Progress of Development of an MOU with MRWPCA on Water Supply Planning and
Funding
No discussion of this item.
7. Report
on Potential for Increasing Capacity of Los Padres Reservoir
The committee agreed to defer this item for six months, and at that time receive an update from District staff.
8. Update
on Status of
No action was taken by the committee on this item.
9. Progress
Report on Aquifer Storage and Recovery Project
General
Manager Fuerst reported that this year, approximately 500 acre-feet of
Schedule Next Meeting Date
The committee members agreed to meet on April 12, 2010 at 9 AM.
Adjournment
The meeting was adjourned at 10:30 AM.
U:\staff\word\committees\WaterSupply\2010\20100503\01\item1_exh1a.doc