EXHIBIT 1-A
MONTEREY PENINSULA WATER
MANAGEMENT DISTRICT
MEMORANDUM
DATE: June
24, 2010
TO: Darby
Fuerst, General Manager
FROM: Andrew
M. Bell, District Engineer
SUBJECT: Progress
Report on Identifying Potential Desalination Project Sites Located within the
MPWMD Boundary
SUMMARY
This
memorandum reports progress to date on identifying potential desalination
projects within the MPWMD boundary. This
effort was directed by the Water Supply Planning Committee at their February 2
and March 8, 2010 meetings.
TASKS AND ESTIMATED
SCHEDULE
1. Develop Feasibility Criteria Goal: March 31, 2010
a. In consultation with the Water Supply
Planning Committee, establish water supply goals and feasibility criteria for
desal projects within the District.
Status: This task was completed at March 8, 2010
Committee meeting. Project locations
were limited to between Cypress Point and the northern extent of the District
boundary. The minimum water supply
production was set at 2,000 acre-feet per year.
2. Literature Search Goal:
April 16, 2010
a. Review
MPWMD reports to determine what sites have been identified and investigated (completed
- see Jan. 25, 2010 memo,
b. Assemble
geologic maps of MPWMD coastline to allow identification of potential locations
of feedwater intake.
Status: This task was completed in
mid-May 2010.
3. Field Surveys Goal:
July 15, 2010
a. Visit all sites that appear may have
potential.
Status:
To be done.
4. Meet with Agencies and Property Owners Goal:
July 15, 2010
a. Meetings
held:
1. City of
2. National Marine Sanctuary
b. Likely additional meeting:
2. City of
c. Possible
meetings:
1. Diana Brooks, DRA
2. Cities of
3.
4. Pebble Beach Company
5. Naval
Status:
I reviewed the environmental and
technical documents on the
I
plan to meet with representatives of the City of
6.
Analyze
Information Collected and Prepare Report on Findings
August 2, 2010
a. Review information collected.
b. Prepare conceptual project designs and
cost estimates for each site identified.
c. Prepare report of findings, including
assessment of feasibility of each site.
Status:
To be done.