DRAFT #1 |
|
MPWMD
Comparative Matrix -- Part I, Desalination Projects |
|
|
|
|
|
|
|
DECISION
ELEMENT |
COASTAL WATER PROJECT |
NORTH
MONTEREY COUNTY DESALINATION PROJECT |
MPWMD 95-10 DESALINATION PROJECT |
|
PROPONENT/SPONSOR |
California American Water |
Pajaro/Sunny Mesa CSD |
MPWMD |
|
|
PROJECT
DESCRIPTION |
Moss Landing desal plant assumes
use of Duke Energy site and intake/outfall.
Includes desal conveyance system comprised of transmission main,
terminal reservoir, and pump stations; and ASR facilities to store CR (or
desalinated) water in Seaside Basin. PEA analyzes Proposed Project and five
alternatives (see Line 60). Proposed
Project yield is 11,730 AFY. |
Desal plant at National
Refractories site; prefer use of Duke Energy wastewater as source (existing
intake as backup) with existing outfall.
Includes energy recovery; possible 30-ac solar energy. Current focus
on regional plant, including P/SM service area; willing to expand to serve
other areas. No ASR is planned, but could be combined with MPWMD ASR project. |
Desal plant at Sand City with
potential intake and outfall locations from Seaside State Beach to coastal
Fort Ord. HDD well technology needed
to achieve 8,409 AF yield goal; brine disposal via MRWPCA outfall likely needed. Could be combined with MPWMD ASR project. |
|
Pilot
Project |
Permits
from Monterey County and California Coastal Commission received in 2006;
installed 2007-2008; ready to begin testing; operate for one year via
agreement with LS Power. |
Permit
from Monterey County received in 2006; California Coastal Commission permit
pending; based on approved Encina plant design; plan to operate 4 yrs.;
managed by Kennedy/Jenks expert |
None planned currently, but will
be required by DHS |
|
PROJECT
YIELD |
Actual yield based on
commitments of purveyor customers |
Actual yield based on
commitments of purveyor customers |
To be determined |
|
Comply
with Order 95-10? Water for Seaside Basin? |
Yes, 10,730 AFY for compliance
with Order 95-10. 1,000 AFY to replace
Cal-Am use in Seaside Basin. |
Yes, 10,730 AFY for compliance
with Order 95-10. 3,000 AF to address
gap between current production and sustainable yield estimate in Seaside
Basin. |
To be determined |
|
Future
Monterey Peninsula Needs? |
Regional Alt includes 3,572 AFY
for jurisdictions within CAW service area as previously identified by MPWMD
and jurisdictions. |
Water for growth not currently
contemplated. |
Water for growth not currently
contemplated. |
|
Future
Non-Monterey Peninsula Needs |
Regional
Alternative lists 4,970 AFY for MCWD/North Mo.Co. as amended by
particpants. North Marina Alt could
also be sized to meet regional needs. |
Up to 11,230 AF to address known
overdraft in areas outside Monterey Peninsula |
None |
|
TOTAL
YIELD |
11,730
AFY for Proposed Project (or North Marina Alternative); 20,272 AFY for
Regional Alternative |
20,000-22,400 AFY (20 MGD
project, capable of producing up to 22,400 AFY - 20,930 AFY demand
identified) |
To be determined |
|
Yield
Phasing to Monterey Peninsula |
11,730
AFY is Proposed Project amount.
Oversized Pipeline Alt or Regional Alt could facilitate incremental
future supply above 11,730 AFY. |
Phasing based on demand; assume
10,730 AF plus amound needed for Seaside first |
No phasing |
|
|
|
PROJECT
COST |
2005 Costs for Proposed Project
(11,730 AFY) Indexed to 2004
through 2008 |
Costs in 2005 dollars for 20 MGD
project provided to B-E/GEI Consultants by Poseidon Resources |
To be determined |
|
|
Capital
- see lines 77-106 |
$178,000,000
for proposed project (11,730 AFY), based on 10%
contingencies.
B-E/GEI: $209,720,000 based on recommended 25% contingencies. |
$132,000,000 for 20 MGD
project
B-E/GEI:
$211,970,000, based on increasing contingencies by 10-15% to 25%) |
To be determined |
|
Amortized
Cap. Cost ($/yr) |
Information not provided
B-E/GEI:
$16,900,000/yr |
Information not provided
B-E/GEI:
$20,080,000/yr |
To be determined |
|
O&M - see lines 108-112 |
$8,440,000/yr.
B-E/GEI:
$8,840,000/yr |
'$16,900,000/yr
B-E/GEI:
$16,900,000/yr |
To be determined |
|
Assumed
energy cost ($/kwh) |
$0.07
- $0.12/kwh |
Information
not provided |
To be determined |
|
Total
Annual Cost |
Information not
provided B-E/GEI: $25,740,000 |
Information not
provided B-E/GEI: $33,980,000/yr |
To be determined |
|
Time
frame for estimates |
Capital
cost escalated through end of construction in 2008 with 4% inflation B-E/GEI: 2007 |
2005
B-E/GEI: 2007 |
N/A |
|
COST TO
PENINSULA |
|
|
|
Share
of total project cost |
100%
of Proposed Project costs are for CAW Peninsula customers; Regional Alt would
rely on prorata share of participation. |
Cost
of water based on contract volume (capacity+annual usage charges); separate
charge for pipelines and pumping facilities. |
Entire cost to be
paid by Peninsula consumers. |
|
How
share determined |
See line 23 |
See line 23 |
N/A |
|
Cost
sharing of existing vs. future Cal-Am ratepayers |
See CPCN application; David
Stephenson testimony |
Future capacity cost based on
construction and transmission |
New users pay connection fee
similar to current system |
|
Cost
of Water ($/AF) |
Proposed Project is $1,725/AF
delivered to Peninsula customers ($1,000/AF for desal plant, pumps, pipes and
storage; $150/AF for ASR; $550/AF for O&M). Includes lease of desal
site. Regional Alternative would be
$1,600/AF for CAW customers. B-E/GEI: $2,190/AF for
Proposed Project, $1,640/AF for Regional Project |
Information not provided by
project proponent. B-E/GEI : $1,520/AF |
To be determined |
|
Impact
to Cal-Am Bill |
Increase of
$2.20/ccf in 2007 to $5.73/ccf in 2011 |
No information provided |
To be determined |
|
|
|
|
FINANCING ASSUMPTIONS |
See CPCN application amended
7/14/05 |
Revenue bonds or COPs; possible
Poseidon funding |
Pursuant to District Law |
|
Interest rate (%) |
7% B-E/GEI: 7% |
Information not provided. B-E/GEI: 7% |
To be determined |
|
Term (yrs) |
30 year. B-E/GEI:
30 years |
Information not provided. B-E/GEI: 30 years |
To be determined |
|
Public
vote required? |
No public vote required;
possible if public financing. CPUC
makes CPCN decision. |
Not required of P/SM unless Prop
218 |
Depends on type of funding or if
part of JPA etc. |
|
Grants
(describe) |
None anticipated at this time. |
On DWR eligible list, but no
grant to date. Will pursue funds for pilot and envtl studies with MLML. |
None currently |
|
|
|
TIMELINE |
See CWP charts |
|
N/A |
|
Draft
EIR (and/or EIS) |
PEA submitted 7/14/05 forms
basis of DEIR, anticipated to be published by CPUC Spring 2007. NEPA requirement uncertain. |
See Line 37 |
To be determined |
|
Certify
FEIR (EIS ROD) |
FEIR anticipated Summer 2007;
NEPA depends on timing of ARMY/FORA land transfer |
June 2008 ("Environmental
Review and Permitting") |
To be determined |
|
Obtain
key permits |
Pilot plant permits: Monterey
County - Aug 2006, but appealed to CCC; RWQCB - Sep 2006; CCC - to be
considered late 2006. Full-Scale
Project: CPUC issuance of CPCN - Sep 2007; CCC Coastal Development Permit
anticipated March 2008 |
Pilot plant permits: Monterey
County - Mar 2006, but appealed to CCC; RWQCB - Sep 2006; CCC - anticipated
to be considered late 2006. See Line 37 for full-scale project permits |
To be determined |
|
Secure
financing |
Upon CPUC approval of CPCN (Sep
2007) |
Information not provided |
To be determined |
|
Secure
ROW/property access |
After FEIR certified by CPUC |
Information not provided |
To be determined |
|
Start
construction |
Winter/Spring 2008 to 2010 |
Information
not provided |
To be determined |
|
Commence
water delivery |
2010 |
July 2010 |
To be determined |
|
Total time to water delivery |
3 1/2 - 4 years from Sep 06 |
4
years from Sep 06 |
To be determined |
|
|
|
PERMITS/REGS |
|
|
|
Federal Agencies |
USEPA, MBNMS, USFWS, NOAA
Fisheries, USACOE, USCG |
Same as CWP except no ASR
permits needed; fewer stream crossings/avoidance lessen federal permits |
Similar to CWP; no pipeline
under sloughs and streams lessens some federal permits |
|
EIS needed? |
NEPA review required; EIS
possible based on pipeline alignment through federal lands if not already
transferred to local jurisdictions |
NEPA
review may be needed by Army for pipes; EIS unlikely if demonstrate
avoidance, reduced impact |
NEPA review assumed; EIS is
possible |
|
Federal
lead agency? |
US Army likely |
To be determined, if needed |
To be determined (US Army?) |
|
Sanctuary
approval? |
Permit to construct; review
NPDES application |
Yes, related to NPDES/outfall;
need to confirm outfall capacity |
Yes, related to intake and
discharge |
|
State
Agencies |
CPUC, SWRCB, RWQCB, SLC, CDFG,
CCC, CEC, CDPH, CDPR, SHPO (CDTS?) |
Same as CWP, except no CPUC,
CEC, or SWRCB |
Same as CWP, except no CPUC,
CEC, or SWRCB |
|
CPUC
approval? |
Needed for Cal-Am rates; CPCN
submitted for CWP Sept 20, 2004 and amended July 14, 2005. |
N/A |
N/A |
|
EIR
lead agency |
CPUC |
Pajaro/Sunny
Mesa CSD |
MPWMD |
|
SWRCB/Water
Rights |
Needed for ASR or any other new
Carmel River diversions |
N/A, no ASR planned |
N/A |
|
Regional
Agencies |
MBUAPCD, MPWMD, TAMC, FORA |
Same as CWP |
Same as CWP |
|
Monterey
County |
MCWRA, MCPBI, MCEH, MCPW |
MCEH, construction and use
permits |
MCEH, MCPBI (?) |
|
Local
Agencies |
All
affected cities and jurisdictions for encroachment and construction permits;
includes MLHD |
Similar to CWP;
jurisdictions may vary; MLHD (?) |
Construction and use permits
within affected jurisdictions |
|
|
|
SITE
CONTROL |
|
|
Confirmed
site? |
Moss
Landing Power Plant planned for pilot plant.
"Duke East" site evaluated in PEA as preferred site. |
Confirmed
site for pilot project. Lease
agreement signed with owner of Natl Refractory site. Potential use of LS Power discharge rather
than own intake; will use own outfall. |
Alternatives identified;
agreement(s) with owner(s) needed, including MRWPCA for use of regional
outfall |
|
Alternative
sites and projects? |
Moss
Landing scenario in PEA evaluates Granite Rock and Natl Refractories
sites.
Five project alternatives in PEA include: (1) Regional Alt with 20,272
AFY yield; (2) Over-sized Pipeline Alt with larger source and transmission
pipelines to enable future supply increases; (3) HDD Intake Alt using HDD
intake wells near MLPP as feedwater supply rather than Duke intake; (4) North
Marina Alt, which locates plant in Armstrong Ranch area with HDD intake and
MLPP outfall for brine; and (5) No Project Alt, comprised of existing
conservation efforts. |
No
alternative to National Refractories site needed. EIR will identify project
alternatives. |
Several locations for
desalination plant, seawater collectors and brine disposal via HDD and MRWPCA
outfall evaluated in BRDEIR, along with other project alternatives. |
|
|
|
OPERATIONS/OTHER |
|
|
Technical,
Managerial and Financial Capabilities (TMF) to meet DHS standards |
Cal-Am has extensive TMF
capabilities and current certifications to own/operate water systems. Over
39,000 customers in Monterey County |
P/SM has current TMF
certification by DHS. Planned enhancement for desal project includes expanded
board and staff; plan to outsource engineering (K/J), legal, development,
contract, admin, construction, management; Poseidon is "Exclusive
Management Agent" in current agreerment. |
Assume certified entity would
operate plant in coordination with Cal-Am system, with MPWMD oversight. |
|
Back-up;
water production interruptions (e.g., power or intake water) |
CWP design is consistent w/ Duke
operations; forebay, storage tanks and ASR as backup; also other Cal-Am
sources in Seaside and CR. |
Own
inake is backup supply if MLPP
discharge water not available; refurbishing seawater tanks with 11-day
supply; generators and onsite solar, if feasible. Notes County Ordinance requires back-up
supply. |
Redundant plant design; back-up
generators; ASR source |
|
|
|
PROJECT
PARTICIPANTS |
|
|
|
Overview |
CAW willing to participate in
public/private partnerships and regional governance formation. Proposed project is geared toward existing
CAW customers. Regional Alternative includes cities and areas within MPWMD,
MoCo, MCWD, Castroville WD and Moss Landing; pending further study and action
by entities. |
Focus on regional plant,
including P/SM needs; willing to expand plant to meet needs of others such as
FORA, MCWD and Monterey Peninsula. |
Funded by MPWMD via methods
allowed by MPWMD Law; possible public-private partnership or JPA. |
|
MPWMD
participation |
MPWMD
and CAW executed April 2006 Management and Operations Agreement regarding ASR
component. No approvals to date. |
P/SM Board authorized JPA with
MPWMD in 2004; MPWMD declined offer at that time. |
MPWMD currently envisioned as
sole sponsor. |
|
Other
entities participation |
Other water purveyors are
wholesale water customers. |
Ongoing discussions with FORA
and MCWD. Met met with Cal-Am in Nov
2004; sent letter in Feb 05. |
None specified; partnerships
possible. |
|
|
|
PUBLIC
INVOLVEMENT |
|
|
Outreach
programs |
Formal outreach program with 52
town hall meetings; presentations to jurisdictions. Website. Direct mail
communication to CAW customers and stakeholders. CPUC staff to facilitate DEIR public
involvement. |
Presentations to MPWMD, City of
Monterey, MCWD, FORA, DHS, Monterey County, MoCo Planning; Castroville WD as
requested |
Monthly written updates and
quarterly public workshops 2002-early 2004. |
|
|
|
INFORMATION
SOURCES |
PEA and Amended Application to
CPUC on CWP dated July 14, 2005, including technical memoranda on engineering
and cost estimates; amended CPCN application for CWP July 2005. Handout materials from CAW consultant (RBF);
matrix input data from RBF July-August 2005, including detailed basis of cost
documents. August 25, 2005 Town Hall Meeting presentation by Steve Leonard of
CAW and responses to questions.
Seawater Desalination Projects Evaluation, B-E/GEI Consultants,
February 20, 2008 |
Application by P/SM to
California Department of Water Resources for Proposition 50 Grant for Pilot
Demonstration Project, March 24, 2006. Monterey Bay Regional Desalination
Project Conceptual Design Report, P/SM in cooperation with Poseidon Resources
Corp., April 2006. Information provided in 2006 by Poseidon Resources to
B-E/GEI Consultants for preparation of desalination projects evaluation.
Seawater Desalination Projects Evaluation, B-E/GEI Consultants, February 20,
2008 |
Board Review Draft EIR, MPWMD
Water Supply Project, December 2003.
Regulatory agency worksheets prepared by Jones & Stokes Sept 2004.
See line 115 for technical reports with cost information. MPWMD consultant studies (CDM). Seawater Desalination Projects Evaluation,
B-E/GEI Consultants, February 20, 2008 |
|
|
|
|
|
CAPITAL
COST DETAIL |
Year 2005 costs indexed to 2004
through 2008 |
Year 2005 costs |
Year 2004 information - December
2002 costs |
|
|
DESALINATION |
|
|
|
Intake |
Included in plant cost |
Information
not provided |
$27,120,000 B-E/GEI: $52,370,000 - $63,5400,000 including brine
discharge |
|
Pre-treatment |
Included in plant cost |
Information
not provided |
Included in plant cost |
|
Desal
Plant |
$84,680,000 B-E/GEI: $90,290,000 |
Information
not provided
B-E/GEI:
$108,470,000 including intake, brine discharge, storage, & pumping
facilities |
$35,470,000
B-E/GEI:
$36,840,000 |
|
Post-treatment |
Included in plant cost |
Information
not provided |
Included in plant cost |
|
Brine
discharge |
Included in intake cost |
Information
not provided |
$23,300,000 - $34,060,000 |
|
Storage |
$5,400,000 includes
term reser, pump station |
Information
not provided |
Included in transmission
pipeline |
|
Transmission
Pipelines |
$22,700,000 B-E/GEI: $24,200,000 |
Information not
provided B-E/GEI: $28,280,000 |
$15,940,000 B-E/GEI: $16,550,000 |
|
Pump
stations |
Included in storage costs |
Information not provided |
Included in transmission
pipeline |
|
Energy
facilities |
None identified |
Information not provided |
$1,260,000 B-E/GEI: $1,300,000 |
|
DESAL
SUBTOTAL |
$112,780,000
B-E/GEI:
$120,250,000 |
Information
not provided
B-E/GEI:
$136,750,000 |
$103,070,000 - $113,840,000 B-E/GEI: $107,050,000 -
$118,230,000 |
|
|
|
|
ASR
COSTS |
$14,120,000 B-E/GEI: $15,060,000 |
N/A |
N/A |
|
RECYCLED
WATER COSTS |
N/A |
N/A |
N/A |
|
|
OTHER
WATER SOURCES |
N/A |
N/A |
N/A |
|
|
|
|
|
|
ADDL
CAPITAL COSTS |
|
|
|
|
Pilot
Plant |
$2,585,000 |
$2,970,000 |
None identified |
|
|
Distribution
system improvements |
Included in desal and ASR costs |
none identified |
None identified |
|
|
Right-of-way |
$2,000,000 (desal plant
site to be leased) |
None identified (desal plant
site to be leased) |
$5,900,000 - $9,100,000
(includes site acquisition) |
|
|
Envtl
review, permits, etc. |
$30,456,000 B-E/GEI: $32,470,000 for Engineering, Overhead,
& Legal |
Information not provided B-E/GEI: $32,820,000 for Engineering, Overhead,
& Legal |
$38,650,000 - $42,690,000 B-E/GEI: $40,140,000 - $44,340,000 for Engineering,
Overhead, & Legal |
|
|
Engineering |
Included in envt/permits |
Information not provided |
Included in envt/permits |
|
|
Construction
Management |
Included in envt/permits |
Information not provided |
Included in envt/permits |
|
|
Admin/legal |
Included in envt/permits |
Information
not provided |
Included in envt/permits |
|
|
Mitigation
measures |
To be determined |
None identified |
To be determined |
|
|
Contingencies |
$15,935,000
B-E/GEI:
$41,940,000 |
Information
not provided
B-E/GEI:
$42,390,000 |
$25,770,000 - $28,460,000
B-E/GEI:
$26,760,000 - $29,560,000 |
|
|
SUBTOTAL |
$50,976,000 |
Information
not provided |
$75,530,000 - $79,160,000
B-E/GEI:
$66,910,0000 - $73,890,000 |
|
|
|
|
|
|
TOTAL
CAPITAL COST |
$178,000,000
for proposed project (11,730 AFY), based on 10%
contingencies.
B-E/GEI: $209,720,000 based on recommended 25% contingencies. |
$132,000,000 for 20 MGD
project
B-E/GEI:
$169,030,000, based on increasing contingencies by 10-15% to 25%) |
$176,200,000
- $193,000,000 B-E/GEI: $173,960,000 -
$192,120,000 |
|
|
|
|
|
|
ANNUAL
O&M COST DETAIL |
|
|
|
Energy |
Included in total O&M |
Information
not provided |
$7,200,000 - $7,550,000
B-E/GEI:
$5,200,000 - $5,550,000 |
|
|
Facilities
O&M |
Included in total O&M |
Information
not provided |
$1,540,000 |
|
|
Mitigation
O&M |
To be determined |
None identified |
To be determined |
|
|
TOTAL
O&M ($/yr) |
$8,440,000/yr.
B-E/GEI:
$8,840,000/yr |
$16,900,000/yr
B-E/GEI:
$16,900,000/yr |
$8,740,000
- $ 9,090,000/yr B-E/GEI: $6,740,000 -
$7,090,000/yr |
|
|
|
|
|
|
|
|
SOURCES
FOR COSTS |
Costs presented in Amended CPCN
Application, July 14, 2005, including detailed Basis of Cost documents and
tables. Seawater Desalination Projects
Evaluation, B-E/GEI Consultants, February 20, 2008 |
Total capital and O&M costs
were provided by Poseidon Resources.
Cost breakdowns were provided to B-E/GEI Consultants under condition
of confidentiality. Pilot plant capital costs are provided in application by P/SM
to California Department of Water Resources for Proposition 50 grant, March
24, 2006. Seawater Desalination
Projects Evaluation, B-E/GEI Consultants, February 20, 2008 |
Monterey Peninsula Water Supply
Project, Phase 2 Technical Memorandum, Project Facilities Alternatives for
the Sand City Desalination Project, June 23, 2004, CDM, p 6-2. Seawater Desalination Projects Evaluation,
B-E/GEI Consultants, February 20, 2008 |
|
|
|
ACRONYMS |
|
$/AF |
cost per acre-foot |
|
$/kwh- |
cost per killowatt-hour |
|
ac |
acre |
|
AFY |
acre-feet per year |
|
ARB |
Air Resources Board |
|
ASR |
aquifer storge and recovery |
|
B-E/GEI |
Bookman-Edmonston/GEI
Consultants |
|
BRAC |
Base Realignment and Closure Office (US Army) |
|
BRDEIR |
Board Review Draft EIR on MPWMD
Water Supply Project (Dec 2003) |
|
Cal-Am |
California American Water |
|
CalTrans |
California Dept. of
Transportation |
|
CAW |
California American Water |
|
CCC |
California Coastal Commission |
|
CDFG |
California Dept. Fish & Game |
|
CDM |
Camp Dresser & McKee Inc. |
|
CDPH |
California Dept. of Public
Health |
|
CDTS |
California Dept. of Toxic
Substances |
|
CEC |
California Energy Commission |
|
CEQA |
California Environmental Quality Act |
|
COP |
Certificate of Participation |
|
CPCN |
Certificate of Public
Convenience and Necessity |
|
CPUC |
California Public Utilities
Commission |
|
CR |
Carmel River |
|
CSD |
Community Services District |
|
CWP |
Coastal Water Project |
|
DBO |
design-build-operate |
|
DEIR |
Draft EIR |
|
DPR |
California Dept. of Parks &
Recreation |
|
Duke |
Duke Energy Corporation |
|
DWR |
California Dept. of Water
Resources |
|
EIR |
Environmental Impact Report |
|
EIS |
Environmental Impact Statement |
|
FEIR |
Final EIR |
|
FORA |
Fort Ord Reuse Authority |
|
HDD |
horizontal directionally-drilled |
|
IS |
Initial Study |
|
JPA |
Joint Powers Authority |
|
K/J |
Kennedy Jenks Engineers, Inc. |
|
MBNMS |
Monterey Bay National Marine Sanctuary |
|
MBUAPCD |
Monterey Bay Unified Air Pollution Control District |
|
MCEH |
Monterey County Environmental Health |
|
MCPBI |
Monterey
County Dept. Planning & Building Inspection |
|
MCPW |
Monterey County Public Works |
|
MCWD |
Marina Coast Water District |
|
MCWRA |
Monterey County Water Resources Agency |
|
MLHD |
Moss Landing Harbor District |
|
MLML |
Moss Landing Marine Laboratory |
|
MLPP |
Moss Landing Power Plant |
|
MoCo |
Monterey County |
|
MP |
Monterey
Peninsula |
|
MPWMD |
Monterey Peninsula Water Management District |
|
MRWPCA |
Monterey Regional Water Pollution Control Agency |
|
N/A |
not applicable |
|
NEPA |
National Environmental Policy Act |
|
NMCDP |
North Monterey County Desalination Project |
|
NOAA Fish |
National Marine Fisheries Service
(part of Natl Oceanic and Atmospheric Administration) |
|
NOP |
Notice of Preparation |
|
NorCo |
North Monterey County |
|
O&M |
operations and maintenance |
|
PEA |
Proponent's Environmental Assessment |
|
P/SM |
Pajaro/Sunny Mesa Community Services District |
|
RBF |
RBF Consulting, Inc |
|
ROD |
Record of Decision |
|
ROW |
right-of-way |
|
RWQCB |
Regional Water Quality Control Board |
|
SHPO |
State Historic Preservation Office |
|
SLC |
State Lands Commission |
|
SRF |
State Revolving
Fund, a loan administered by SWRCB |
|
SWRCB |
State Water Resources Control Board |
|
TAMC |
Transportation Agency of Monterey County |
|
TBD |
to be determined |
|
USACOE |
US Army Corps of Engineers |
|
USBLM |
US Bureau of Land Management |
|
USBR |
US Bureau of Reclamation |
|
USCG |
US Coast Guard |
|
USEPA |
US Environmental Protection Agency |
|
USFWS |
US Fish & Wildlife Service |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|