WATER SUPPLY PLANNING
COMMITTEE
ITEM: |
ACTION
ITEMS |
||||
|
|||||
6. |
(This
item is listed as item 2.A on the revised committee meeting agenda) DISCUSS
FEASIBILITY OF MOVING ADDITIONAL WATER FROM CARMEL VALLEY TO WATER PROJECTS 1
AND 2 |
||||
|
|||||
Meeting Date: |
May 4, 2011
|
|
|
||
|
|||||
From: |
|
|
|
||
|
General Manager |
|
|||
|
|
|
|||
Prepared By: |
Larry
Hampson |
|
|
||
SUMMARY: The yield of the
Seaside Groundwater Basin (SGB) Aquifer and Storage Recovery Project is currently
constrained by several bottlenecks in the existing CAW system
infrastructure. Depending on the target
level of flow between
BACKGROUND: The CAW system
is a patchwork of systems that began with a design to move water from San
Clemente Dam to the
The Cal-Am Coastal Water Project Final Environmental Impact Report, October 2009, contains a description of two alternative pipeline routes and the infrastructure necessary to increase the flow of water between Carmel Valley and Seaside (see Exhibit 6-A, will be presented at the May 4, 2011 meeting). Staff will present additional information concerning these alternatives at the May 4, 2011 Water Supply Planning Committee meeting.
EXHIBITS
6-A APPENDIX M Memorandum: Segunda Pipeline Alternatives Analysis, RBF Consulting, February 14, 2007 (Will be presented at the May 4, 2011 committee meeting.)
U:\staff\word\committees\WaterSupply\2011\20110504\06\item6.docx