WATER SUPPLY PLANNING
COMMITTEE |
|||||
|
|||||
ITEM: |
ACTION ITEM |
||||
|
|||||
3. |
CONSIDER
REQUEST FROM PUBLIC OUTREACH COMMITTEE THAT THE WATER SUPPLY PLANNING
COMMITTEE EVALUATE DESALINATION PROJECT ALTERNATIVES |
||||
|
|||||
Meeting
Date: |
June 7, 2012 |
Budgeted: |
N/A |
||
|
|||||
From: |
David J.
Stoldt, |
Program/ |
N/A |
||
|
General
Manager |
Line Item No.: |
|||
|
|||||
Prepared
By: |
David J.
Stoldt |
Cost
Estimate: |
N/A |
||
|
|||||
General Counsel Review: N/A |
|||||
Committee Recommendation: N/A |
|||||
CEQA Compliance: N/A |
|||||
SUMMARY: At its May 9, 2012 meeting, the Public Outreach
Committee agreed to ask the Water Supply Planning Committee to consider
evaluating each of the three potential desalination projects on a common basis
in order to ascertain the viability of each project relative to the others. This task is similar to a request made of the
Technical Advisory Committee by the MPRWA.
A verbal report will be provided on the status of the MPRWA’s progress.
RECOMMENDATION: The General Manager recommends that the Committee discuss and recommend a position for Board Approval at the June 12, 2012 board meeting.
DISCUSSION: Three items from the MPWRA technical advisory committee are attached:
a) A draft evaluation matrix
b) An proposed Request for Proposals for cost
evaluation, to be discussed at the May 31, 2012 JPA meeting
c) A list of possible consultants for
distribution of the RFP
EXHIBITS
3-A Draft Evaluation Matrix
3-B Draft Request for Proposals for Comparison of Cost Estimates for the
Desalination Projects and Evaluation of Alternative Financing Options
3-C List of Possible Consultants for Distribution of the RFP
U:\staff\Board_Committees\WSP\2012\20120607\03\item3.docx