EXHIBIT
1-A DRAFT
MINUTES |
|
|||
Water
Supply Planning Committee of the Monterey
Peninsula Water Management District March 4, 2014 |
|||||
|
|
|
|||
Call to Order |
The
meeting was called order at 8:12 am in the Water Management District
conference room. |
||||
|
|||||
Committee members present: |
Jeanne
Byrne |
||||
|
David
Pendergrass |
||||
|
|
||||
Committee members absent: |
Robert
Brower |
||||
|
|
|
|||
Staff members present: |
David
Stoldt, General Manager |
||||
|
Larry
Hampson, Planning & Engineering Division Manager |
||||
|
Arlene
Tavani, Executive Assistant |
||||
|
|
|
|||
District Counsel present: |
David
Laredo |
|
|||
|
|
|
|||
Comments from the Public |
No
comments. |
||||
|
|||||
Action Items |
|
||||
1. |
Consider Adoption of February
18, 2014 Committee Meeting Minutes |
||||
|
On
a motion by Pendergrass and second of Byrne, the minutes were adopted
unanimously on a vote of Pendergrass and Byrne. |
||||
|
|
||||
2. |
Develop Recommendation to the
Board on Authorization to Increase Budget for Groundwater Replenishment
Project (GWR) |
||||
|
On
a motion by Pendergrass and second of Bryne the committee voted unanimously
to recommend that the Board of Directors increase budgeted expenditures for
the Groundwater Replenishment Project by $938,851 for Fiscal Year 2013-2014
and approve Amendment 1 to the Cost Sharing Agreement. The motion was approved on a vote of
Pendergrass and Byrne. No comments were directed to the committee
during the public comment period on this item. |
||||
|
|
||||
Discussion Items |
|||||
3. |
Progress Report on GWR
Development from Representative to Joint Ad-Hoc GWR Committee |
||||
|
The
committee discussed communications with the Joint Ad-Hoc Groundwater
Replenishment (GWR) Committee and parties that control intake water sources.
The goal is to develop terms and conditions for GWR source water agreements.
Stoldt reviewed charts that describe alternatives for GWR source water,
including diversions of flows in the Blanco Drain and Reclamation Ditch to
the Monterey Regional Water Pollution Control Agency (MRWPCA) treatment
facility for incorporation into the GWR for use on the Monterey Peninsula.
The Blanco Drain and Reclamation Ditch waters could also potentially be
treated at new facilities to be constructed by Salinas Valley interests and
distributed to beneficiaries that have contracted for purchase of the water. Staff also reported that
Monterey County has a right to divert up to 135,000 acre-feet per year (AFY) from the Salinas River under a
permit that dates from 1957. SWRCB threatened
to revoke the permit for lack of due diligence in completing work necessary
to appropriate water. The State Water Resources Control Agency and
MCWRA agreed to settle the matter with a reduction in the face amount of the
right from 168,000 AFY to 135,000 AFY. In addition, SWRCB set an
aggressive schedule that includes several milestones culminating with
construction of a project by July 1, 2026. By July 2015 the County must
provide to the state, a financing plan to fund a project that will utilize
that water right. The challenge for the County is to convert the water right
to an annual right with a diversion point close to the coast. The two
existing points of diversion are near Soledad and Spreckels. Water Management
staff believes that the prohibition against transfer of water from the
Salinas aquifer to the Peninsula relates only to groundwater. There are
various proposals for use of the County’s water right. (1) Utilize the
surface water right for all the City of Salinas’ water needs. However,
storage and conveyance facilities would need to be planned and
constructed. (2) The Water Management District could purchase a portion
of the County’s surface water, which would provide water for the Peninsula
and funding for other County water infrastructure projects. |
||||
|
|||||
Suggestions from the Public on
Water Supply Project Alternatives |
|||||
No
comments. |
|||||
|
|
||||
Set Next Meeting Date |
|||||
A
meeting date was not set. At the April
2014 committee meeting, the committee should review the revised Los Padres
Dam and Reservoir Long-Term Strategic and Short-Term Tactical Plan. |
|||||
|
|
||||
Adjournment |
|||||
The
meeting was adjourned at 9:15 am. U:\staff\Board_Committees\WSP\2014\20140522\01\item1_exh1a.docx |
|||||
|
|||||