ITEM: |
DISCUSSION
ITEMS |
||||
|
|||||
3. |
RECEIVE AND DISCUSS THE
KENEDDY/JENKS CONSULTANTS REPORT “EVALUATION OF THE DEEP WATER DESALINATION
PROJECT COSTS” |
||||
|
|||||
Meeting
Date: |
September 18, 2014 |
Budgeted: |
N/A |
||
|
|||||
From: |
David J.
Stoldt |
Program/ |
1-11-1 |
||
|
General
Manager |
Line Item No.: N/A |
|||
|
|||||
Prepared
By: |
David J.
Stoldt |
Cost Estimate: |
N/A |
||
|
|||||
General Counsel Approval: N/A |
|||||
Committee Recommendation: |
|||||
CEQA Compliance: N/A |
|||||
SUMMARY: At
its April 21, 2014 meeting the Board directed staff to enter into a
cost-sharing relationship with Soquel Creek Water District to evaluate capital
and operating cost projections of the DeepWater
Desalination project and to determine the approximate cost-per-acre-foot of delivered
water was. The firm of Kennedy/Jenks has
completed its third party review which is attached as Exhibit 3-A.
RECOMMENDATION: The
Committee should discuss the report and direct the General Manager to address
any follow-up questions with the consultant.
DISCUSSION:
The consultant performed an evaluation of the DeepWater
Desal (DWD) Group’s projected unit water cost
(capital and O&M) costs for the a “Joint Powers Authority” (JPA)
Desalination Facility part of the overall DWD Project. They also provided
estimated O&M costs for the treated water distribution pipelines to develop
a unit cost of water delivered to the Cal-Am system.
The table below compares the projected total
unit water costs for the JPA Desalination Facility providing 6,000 AFY of water
to MPWMD. The unit cost of the JPA Desalination Facility component is based on
10,000 AFY production and relies on full JPA Member subscription to a take or
pay contract. If the project is not fully subscribed, the JPA Desalination
facility would have a higher unit cost.
Kennedy/Jenks opinion of probable total unit
water cost for the JPA Desalination Facility part of the DWD Project is
approximately 15 percent higher than the projected DWD unit water cost,
primarily due to the higher unit energy costs ($300 per AF for renewable
energy) and the higher percentage of contingency. With a focus on project cost
control during construction, and a low energy rate obtained through the City of
Salinas, it is reasonable that the proposed JPA Desalination Facility could
provide delivered water to Cal-Am’s service territory in the range of $1,700 to
$2,100 per AF.
Project Cost Component Kennedy/Jenks
Estimate DWD Estimate
Desalination Facility Annual Bond Payments $600 $500
Desalination Facility O&M $800 $500
Intake/Outfall O&M Share $65 $50
JPA Desalination Facility Subtotal, $/AF $1,465
$1,050
Distribution System Annual Bond Payments $500 $500
Distribution System O&M $120 $120
Distribution System Subtotal, $/AF $620 $620
Total Unit Water Cost ($/AF) $2,085 $1,670
EXHIBIT
3-A Report:
Evaluation Of The Deep Water Desalination Project Costs
U:\staff\Board_Committees\WSP\2014\20140918\03\item3.docx