WATER SUPPLY PLANNING
COMMITTEE
ITEM: |
DISCUSSION
ITEM |
||||
|
|||||
8. |
UPDATE ON ASR ACTIVITIES |
||||
|
|||||
Meeting
Date: |
April 5, 2016 |
Budgeted: |
N/A |
||
|
|||||
From: |
David J.
Stoldt |
Program/ |
|
||
|
General
Manager |
Line Item No.: N/A |
|||
|
|||||
Prepared
By: |
David J.
Stoldt |
Cost Estimate: |
N/A |
||
|
|||||
General Counsel Approval: N/A |
|||||
Committee Recommendation: |
|||||
CEQA Compliance: N/A |
|||||
SUMMARY: Aquifer
Storage and Recovery (ASR) injection began January 7, 2016. There have been four periods to date where
conditions have allowed injection, the most recent of which has been 25 consecutive
days through March 30th with additional days expected.
Performance through March 30, 2016 by well is summarized below:
Well |
Amount |
ASR 1 |
140.18 |
ASR 2 |
328.25 |
ASR 3 |
151.58 |
ASR 4 |
4.35 |
Total |
624.35 |
The injection by permit is summarized below:
Permit |
Amount |
20808 A |
183.14 |
20808 C |
441.21 |
Total |
624.35 |
EXHIBIT
None
U:\staff\Board_Committees\WSP\2016\20160405\08\Item
8.docx