WATER SUPPLY PLANNING
COMMITTEE
ITEM: |
DISCUSSION
ITEM |
||||
|
|||||
9. |
UPDATE ON PURE WATER
MONTEREY PROJECT |
||||
|
|||||
Meeting
Date: |
April 5, 2016 |
Budgeted: |
N/A |
||
|
|||||
From: |
David J.
Stoldt |
Program/ |
|
||
|
General
Manager |
Line Item No.: N/A |
|||
|
|||||
Prepared
By: |
David J.
Stoldt |
Cost Estimate: |
N/A |
||
|
|||||
General Counsel Approval: N/A |
|||||
Committee Recommendation: |
|||||
CEQA Compliance: N/A |
|||||
SUMMARY:
California Public Utilities
Commission (CPUC) proceeding –
Rebuttal testimony was filed March 22, 2016.
The CPUC Office of Ratepayer Advocates (ORA) provides the following
findings regarding the GWR Determination:
A. Supplemental testimony demonstrates that
GWR has met the first eight findings detailed in the Settlement Agreement.
B. Supplemental testimony demonstrates that
GWR coupled with a 6.4 MGD desalination plant provides numerous positive
benefits in comparison to a 9.6 MGD desalination plant.
C. The
GWR Project and the Desalination Project currently have differing levels of certainty.
D. There is no projected debt equivalence
associated with Cal Am entering into the WPA for GWR Project water.
E. There are inconsistencies in MPWMD and Cal
Am cost analyses.
F. Cost analyses submitted in Supplemental
Testimony indicate that, compared to the 9.6 MGD Desalination Plant, the 6.4
MGD Desalination Plant with GWR project would likely result in: 1) a small
first year revenue requirement premium; and 2) either a small net present value
(NPV) premium or small NPV benefit.
G. The ninth finding required by the
Settlement Agreement has not been met. The ninth finding is that the revenue
requirement for the combination of the GWR Project and the smaller desalination
project is just and reasonable when compared to the revenue requirement for a
larger desalination project alone. ORA stated “given the existing terms of the
WPA, the revenue requirement for the GWR/Small Desal
Option is currently undefined, and unbounded.”
H. The terms set forth in the Settlement
Agreement as prerequisites for Cal Am entering into a Water Purchase Agreement
(WPA) for GWR water have not yet been met, but could be met by modifying the
WPA.
Based on these findings, ORA recommends that: The Commission should
authorize Cal Am to enter into the WPA for GWR if and only if the WPA is
modified such that: 1) the language deeming all costs just and reasonable is
removed, and 2) a reasonable and prudent cost cap on the price of GWR purchased
water is including in the WPA. The
District believes that these two conditions can be met, and in fact included a
proposed cost cap in its rebuttal testimony filed the same day. ORA testimony is attached as Exhibit 9-A.
The District’s testimony included updated cost analyses shown below and
proposed a cost cap of water equal to $1720 in the first year of operations.
Cost of Water Alternatives for Pure Water Monterey (GWR)
Variable |
Scenario A |
Scenario B |
Scenario C |
Scenario D |
Cal-Am Revenue Requirement1 |
Updated |
Updated |
Updated |
Updated |
Outfall Rental |
Same as Jan |
Same as Jan |
Same as Jan |
Same as Jan |
Replacement Costs |
Same as Jan |
Same as Jan |
Same as Jan |
Same as Jan |
Energy Escalation |
4.80% |
4.80%@72% |
4.80%@72% |
4.80%@72% |
Non-Labor Escalation |
1.90% |
1.90% |
1.90% |
1.90% |
Labor Escalation |
1.74% |
1.74% |
1.74% |
1.74% |
Project Cost (excl. Pipeline) |
$57.53 mil |
$57.53 mil |
$57.53 mil |
$57.53 mil |
Project Cost General Contingency |
29% |
29% |
20% |
20% |
SRF Loan Rate & Term |
1.0% / 30 yr |
1.0% / 30 yr |
1.0% / 30 yr |
1.0% / 30 yr |
SRF Grants to Project |
$0 |
$0 |
$0 |
$7.50 mil |
Reimbursement of Pre- Costs |
$5.00 mil |
$5.00 mil |
$5.00 mil |
$5.00 mil |
MCWRA Contribution |
$3.90 mil |
$3.90 mil |
$3.90 mil |
$3.90 mil |
Pipeline Cost |
$26.97 mil |
$26.97 mil |
$26.97 mil |
$26.97 mil |
Pipeline Cost Contingency |
30% |
30% |
30% |
30% |
SRF Loan Rate & Term |
1.8% / 30 yr |
1.8% / 30 yr |
1.8% / 30 yr |
1.8% / 30 yr |
SRF Grants to Pipeline |
$0 |
$0 |
$0 |
$2.50 mil |
FORA Grants to Pipeline |
$4.62 mil |
$4.62 mil |
$4.62 mil |
$4.62 mil |
|
|
|
|
|
GWR NPV Advantage/(Disadvantage) |
($7.77) mil |
$1.14 mil |
$3.02 mil |
$8.69 mil |
GWR Overall Advantage/(Disadvantage) |
$2.14 mil |
$22.72 mil |
$26.39 mil |
$37.4 mil |
GWR Cost of Water – Yr 1 |
$1,802 |
$1,710 |
$1,675 |
$1,569 |
6.4 MGD Cost of Water2 – Yr 1 |
$6,318 |
$6,318 |
$6,318 |
$6,318 |
9.6 MGD Cost of Water – Yr 1 |
$4,532 |
$4,532 |
$4,532 |
$4,532 |
6.4 MGD + GWR Cost of Water – Yr 1 |
$4,697 |
$4,664 |
$4,652 |
$4,614 |
Monterey Regional Water Pollution Control Agency (MRWPCA) submitted
testimony (Exhibit 9-C and Exhibit 9-D) with new information on Pure Water
Monterey Project costs, possible savings in the cost of the desalination
alternatives, and water quality issues, as well as included letters of support
from the following:
·
Senator
Diane Feinstein
·
Congressman
Sam Farr
·
State
Senator William Monning
·
Assemblymember Mark
Stone
·
County
Supervisor Dave Potter
·
County
Supervisor John Phillips
·
State
Water Resources Control Board Felicia Marcus, Chair
·
Fort Ord
Reuse Authority
Water Rights – Six letters were received from National Marine
Fisheries Service (NMFS) and California Department of Fish and Wildlife (CDFW)
(dated February 16, 2016) that were protests to water rights applications
A032263A (Blanco Drain Diversion), A032263B (Reclamation Ditch Diversion), and
A032263C (Tembladero Slough Diversion). MRWPCA, MCWRA, and MPWMD staff and
engineering consultants are working with Denise Duffy and Associates (DD&A)
to review the letters submitted, determine assignments and technical studies
and expertise needed to respond, and to make assignments to the technical team,
agency/district staff, and various attorneys. DD&A will focus the technical
consultants on key information and analyses needed, and coordinate with the
team toward successful completion of the protest responses.
Response letters were prepared and delivered March 18, 2016. A technical team meeting has been scheduled
on April 5th in Salinas. It
is hoped that the parties can negotiate a resolution to the protests.
Energy Agreement – On March 28th, the MRWPCA Board
approved an agreement for the purchase of energy to run Pure Water Monterey
with the Monterey Regional Waste Management District (MRWMD.) MRWMD utilizes biogas produced by the
decomposition of waste material in the landfill to produce electrical energy.
MRWMD’s biogas power generation facility contains four internal combustion
engine-generators. MRWMD is currently in
the process of replacing/repairing two of the four units. When this work is
complete, MRWMD will have the capability to produce approximately 5,000 kilowatthours (kWh) of electrical energy. The estimated
future electrical demand for MRWMD is approximately 3,000 kWh. Therefore, MRWMD
will have approximately 2,000 kWh of surplus electrical energy available for
export and sale.
MRWPCA is currently in the process of designing the Advanced Water
Treatment Facility (AWTF) for the Pure Water Monterey project to be located at
the Regional Treatment Plant (RTP), which is adjacent to the landfill and power
generation facility operated by MRWMD. The projected electrical demand of the
AWTF is approximately 2,000 kWh, which is similar to the amount of excess power
that could be generated by MRWMD. Staff
from MRWPCA and MRWMD has determined that it is to the benefit of both agencies
for MRWMD to make the surplus energy generated by their power generation
facility available for sale to and use by MRWPCA to meet the increased
electrical demand produced by the AWTF. Staff from both agencies met and
drafted the electric power purchase agreement between MRWPCA and MRWMD.
The highlights of the agreement are as follows:
·
MRWMD
will produce for export and sale to MRWPCA a minimum of 1,800 kWh of electrical
power with an availability rate of 90%.
·
MRWPCA
will take or pay for a minimum of 1,800 kWh of electricity to power the AWTF.
·
MRWPCA
will pay MRWMD a rate equal to Pacific Gas and Electric’s Industrial Rate
Schedule, E-20 Primary Firm, Winter Off-peak Energy Charge, to be adjusted each
July 1. (This equates to $0.08053 per kWh at the current rate).
·
The term
of the agreement shall be for an initial term of 20 years to be extended for an
agreed upon period or periods on the same terms.
·
MRWMD
will be responsible for the cost of the installation, operation, maintenance, and
repair of all equipment and facilities up to, and including, the electrical
usage meter used for billing MRWPCA.
·
MRWPCA
will be responsible for the cost of installation, operation, maintenance, and repair
of all equipment after the electrical usage meter.
·
MRWMD
will provide MRWPCA an easement from the electrical usage meter to the fence
line of the two agencies for the installation and maintenance of the conductors
necessary to transport the power between the two agencies.
·
The
agreement will be terminated should the AWTF not be constructed.
Fort Ord Reuse Authority – Authorized Executive Officer to negotiate a
Memorandum of Understanding with MCWD to designate up to $6M of the Capital
Improvement Program's (CIP's) water augmentation budget ($24M) to the Regional
Urban Water Augmentation Project's (RUWAP's) direct construction costs of the
recycled water pipeline, dependent on Pure Water Monterey's project approval by
the California Public Utilities Commission (CPUC) and the completion of
milestones approved by the three agency boards.
Rec Ditch/Blanco Drain
Project – The kickoff meeting
with E2 was held on February 25,
2016. MRWPCA staff has initiated contact with property owners regarding
access and Rights-of-Way. Regulatory
activity includes follow-up on the water rights applications and applying for a
Stream Bed Alteration agreement for work in
the riparian corridor.
Advanced Water Treatment
Facilities - The kickoff
meeting with Kennedy Jenks (KJ) was held on February 4, 2016. KJ is well
underway with the design work. Assumptions about the initial sizing of the
plant have been agreed upon and we anticipate receiving the 30% design
submittal for the end of April.
Injection Facilities –A pre-proposal meeting on the GWR Injection
Well project took place on February 17. Several firms attended the mandatory
meeting. On March 11th, two proposals were received from E2 Consulting
Engineers, Inc. (E2) and Kennedy/Jenks Consultants (KJ) for the GWR Injection
Well Facilities Project.
The GWR Injection Well Facilities design has already been developed to
the 10% design level by E2 Consulting Engineers. This contract will be
performed in two phases with the successful Consultant expected to complete the
Phase 1 Final Bid plans and specifications package, performing Phase 1 Bid
Phase Services, and then continue on to provide Engineering Services During
Construction for Phase 1 before repeating the same tasks for Phase 2, and
finally As-Built Drawings. The initial phase of work will include the
installation of one deep injection well and one monitoring well for testing to
reduce the hydro geologic uncertainty associated with the GWR injection wells
and to collect data needed for successful implementation of Phase 2. Phase 2
will include the installation of an additional deep injection well, a vadose
zone well, and three monitoring well clusters. The results of the Phase 1 field
testing will be used to modify the Technical Specifications for the Phase 2
wells. The Consultant will be required to request and obtain a
Notice-to-Proceed for each task prior to proceeding with additional work.
A committee of five met on Monday, March 14, 2016 to select a firm to do
the project. The committee unanimously selected Kennedy/Jenks for the depth of
information included in their proposal, including several options for value
engineering that will benefit the Agency and bring down overall cost. On March 28th, the MRWPCA board
approved hiring KJ.
Water Conveyance Pipeline – The Recycled Water Committee and Board are
well aware of the ongoing discussions with Marina Coast Water District on the
pipeline agreement. Both entities are working through comments on the
agreement. Substantial progress has been made on key issues. Upon finalization,
an agreement will be brought before the Board pending MCWD approval. MRWPCA
staff has been in contact with US Army real estate department to initiate the
process of gaining approvals for rights-of-way through Fort Ord.
EXHIBITS
9-A Office of Ratepayer Advocates Rebuttal
Testimony
9-B David Stoldt (MPWMD) Rebuttal Testimony
9-C Paul Sciuto
(MRWPCA) Rebuttal Testimony
9-D Margaret Nellor
(MRWPCA) Rebuttal Testimony
U:\staff\Board_Committees\WSP\2016\20160405\09\Item-9.docx