WATER SUPPLY PLANNING COMMITTEE |
||||
|
||||
ACTION ITEM |
||||
|
||||
2. |
CONSIDER ADOPTION OF
REIMBURSEMENT METHODOLOGY AND AMENDMENT 2 TO COST SHARING AGREEMENT FOR PURE
WATER MONTEREY |
|||
|
||||
Meeting Date: |
October 17, 2017 |
Budgeted: |
N/A |
|
|
||||
From: |
David J. Stoldt |
Program/ |
|
|
|
General Manager |
Line Item No.: |
N/A |
|
|
||||
Prepared By: |
David J. Stoldt |
Cost Estimate: |
N/A |
|
|
||||
General Counsel Approval: N/A |
||||
Committee Recommendation: N/A |
||||
CEQA Compliance: Action does not constitute a project as
defined by the California Environmental Quality Act Guidelines section 15378. |
||||
SUMMARY:
In May 2013, the
Monterey Peninsula Water Management District (District) entered into a Cost
Sharing Agreement (Agreement) with Monterey One Water (MOW, at the time
Monterey Regional Water Pollution Control Agency) to fund the Groundwater
Replenishment (GWR) Project planning and development costs, also referred to as
pre-construction costs.
In April
of 2017, MOW’s State Revolving Fund Loan was approved to support the payment of
GWR/Pure Water Monterey (PWM) project costs, providing the opportunity to
reimburse pre-construction costs from the State Revolving Fund loan.
To
formalize this action, as well as incorporate additional terms to support the
continued relationship between the parties, a second Amendment to the Cost
Sharing Agreement is needed.
MOW’s
Budget and Personnel Committee (BPC) met to discuss the amendment at its
September 8, 2017 meeting, at which time the BPC directed MOW staff to pursue
reimbursement of MOW funds; however, they suggested that consideration be given
to the District waiving reimbursement of their costs, for reasons described
under “BACKGROUND” below.
At the
District’s September 11, 2017 Administrative Committee meeting, the Committee
approved the proposed form of amendment, as well as an alternate version, where
the District would not participate in funding the debt service reserve fund and
the initial reimbursement proportions would be different.
The
District’s full board approved either of both versions on consent at its
September 18, 2017 meeting.
At MOW’s
September 25, 2017 full board meeting, the reimbursement proposals were
discussed and staff was directed to develop a series of talking points to be
conveyed to the District by the MOW board Chair, in support of the District
giving consideration to waiving reimbursement of their costs. Such talking points are summarized under
“BACKGROUND” below.
Both
parties’ board Chairs and general managers met on October 4, 2017, at which
time the District strongly expressed that it does not agree to waive its
reimbursement. The District also
provided its own talking points in response to MOW, which are summarized under
“BACKGROUND” below.
As a
result of the discussion between the parties on October 4th, the
board Chairs and general managers agree that the revised proposal (Exhibit 2-A) hereto represents a compromise which (i) is fair to both parties,
(ii) provides for potential future reimbursement of pre-construction costs in a
manner that bring both parties closer to proportional reimbursement, and (iii)
leave the door open for a future contribution by the District to help reduce
the wholesale cost of product water.
RECOMMENDATION:
The General
Manager recommends the Committee recommend the Board approve Amendment 2
to the Cost Sharing Agreement with MOW for the Pure Water Monterey
Project.
BACKGROUND:
Under the Cost
Sharing Agreement adopted in May 2013, beginning with Fiscal Year 2013-14, MOW
agreed to fund 25% of all costs listed in Section II (A)(1, 2) of the
Agreement, while the District agreed to pay for 75% of the specified costs. In
July 2016, the parties entered into Amendment 1 to the Cost Sharing Agreement
to increase the number of fully-funded MOW positions covered and support the
costs associated with the line of credit.
After approval
of MOW’s State Revolving Fund Loan in April of this year, project costs through
February 28, 2017 concluded the pre-construction costs covered by the Cost
Sharing Agreement. All eligible costs incurred after that period were paid by
MOW and subject to reimbursement by the State.
Staff of
MOW and the District agreed to apply for $8.2 million in initial reimbursements
from the State Revolving Fund loan, in concept with the reimbursement shared
equally between the organizations. The Agency’s $4.1 million share of the
reimbursements was earmarked to replenish and increase reserve balances.
At the
September 8, 2017 MOW BPC meeting, there were still on-going discussions
between both parties. Staff was initially considering a recommendation for an
equal distribution of the $8.2 million initial reimbursement, an equivalent
contribution to establish the PWM debt service fund, and that any future
distributions be based on the proportional share of costs or a true-up to that
level. As stated above, at the BPC meeting, MOW staff was directed to pursue
reimbursement of MOW funds, and to suggest that the District give consideration
to waiving reimbursement of their costs.
MOW Talking Points: On October 3, 2017, MOW provided to the District several talking
points for giving consideration to waiving its reimbursement. The points are summarized below:
District Talking
Points:
On October
4, 2017, the District provided to MOW several talking points for giving
consideration to waiving its reimbursement.
The points are summarized below:
Proposed Revised
Amendment 2: After having met to discuss the matter, the
parties propose the attached revised Amendment 2 to the Cost Sharing Agreement
(Exhibit 2-A.)
Key
provisions are listed below:
Planning
and Development Costs Definition
Amends
the existing planning and development costs definition.
Add
Reimbursement of Planning and Development Costs
Adds
a new section to address the planning and development costs reimbursed through
the State Revolving Fund (SRF) Loan. This section provides for a 50%-50%
initial reimbursement share for each agency and addresses how subsequent
reimbursements would be shared between the two agencies, targeting a goal of
bringing both parties back in line with proportional reimbursement after
subsequent reimbursements.
Add
Unreimbursed Construction Period Costs
Adds
a new section to address project-related costs that are not allowed to be paid
through the SRF loan between March 1, 2017 to June 30, 2019. The State is disallowing certain costs that
are not associated with the project design and construction. Such costs include
public outreach, regulatory proceedings, groundwater modeling, geochemical
monitoring, and regulatory proceedings. This section would provide a mechanism
of continued cost sharing on unreimbursed costs.
Add
Financing of GWR Unreimbursed Construction Period Costs
Adds
a section to state that the District shall pay seventy-five percent (75%) of
the Unreimbursed Construction Period costs and MOW shall pay twenty-five
percent (25%) of such costs.
Add
Debt Service Reserve Fund
Adds
a section to address funding the debt service reserve fund. Unlike earlier proposals,
there is no shared funding agreement at this time and MOW retains the right to
address alternative approaches for the funding of the reserve at the in-service
date in the future.
Amending
Term
Amends
the existing term of the Agreement to remain in effect until June 30,
2019. An extension could occur at the
agreement of the parties.
EXHIBITS
2-A Proposed Amendment 2 to MRWPCA-MPWMD Groundwater Replenishment
Project Cost Sharing Agreement
U:\staff\Board_Committees\WSP\2017\20171017\02\Item-2.docx