WATER SUPPLY
PLANNING COMMITTEE |
||||
|
||||
PRESENTATION |
||||
|
||||
4. |
REVIEW OF CEASE AND DESIST
ORDER MILESTONES |
|||
|
||||
Meeting Date: |
July 6, 2020 |
Budgeted: |
N/A |
|
|
||||
From: |
David J. Stoldt |
Program/ |
|
|
|
General Manager |
Line Item No.: |
N/A |
|
|
||||
Prepared By: |
David J. Stoldt |
Cost Estimate: |
N/A |
|
|
||||
General Counsel Approval: N/A |
||||
Committee Recommendation: |
||||
CEQA Compliance: This action does not constitute a project
as defined by the California Environmental Quality Act
Guidelines Section 15378. |
||||
SUMMARY: On April 29, 2020 California American Water (Cal-Am) filed with
the State Water Resources Control Board its 2nd Quarterly Report for the
2019-2020 Water Year Addressing Operations for the Period of January 1, 2020 to
March 31, 2020. Such a report is
required under the extended Cease and Desist Order (CDO). That compliance filing included the following
passages (emphasis added):
·
Milestone
5, Water Year 2019-2020 ((1) Drilling activity for at least one MPWSP
Desalination Plant source water production well complete; (2) foundation and
structural framing complete for MPWSP Desalination Plant pretreatment seawater
reverse osmosis, and administration buildings at desalination plant; (3)
excavation complete for MPWSP Desalination Plant brine and backwash storage basins;
and (4) 25% of Desalination Plant transmission pipelines installed based on
total length, including 100% installation of the "Monterey Pipeline and
other ASR related improvements".)
·
The
stay on physical construction of the desalination plant imposed by the Monterey
Superior Court currently remains in place until at least April 21, 2020.
Although Cal-Am had been on track to complete permitting and begin construction
activities at the site, the court's stay precludes Cal-Am from starting the
necessary activities at the plant site in order to be able to complete
construction of the various plant facilities required under Milestone 5 by
September 30, 2020. It is therefore unlikely that Cal-Am will be able to
complete all of the activities required under Milestone
5 by September 30, 2020. This setback resulting from the court's stay is beyond
Cal-Am's control.
·
The
Coastal Commission has not set a date for the continued hearing and
determination on Cal-Am's application for a coastal
development permit for the project's slant wells. Without a permit, Cal-Am
cannot begin the necessary activities in order to complete drilling activities
for a slant well, as required under Milestone 5. The delay caused by the
Coastal Commission's decision to continue the hearing, based on a determination
made just 10 days before the scheduled hearing that additional investigation
was required, is beyond Cal-Am's control.
This highlights a need to revisit what the CDO
milestones dictate going forward.
Attached as Exhibit 4-A are the
milestones as incorporated in WR 2016-0016, Section 3.b.v and vi.
EXHIBIT
4-A Milestones
Under the CDO
U:\staff\Board_Committees\WSP\2020\20200706\04\Item-4.docx