ITEM: |
CONSENT CALENDAR |
||||
|
|||||
4. |
CONSIDER AUTHORIZATION OF REIMBURSEMENT AGREEMENT WITH
FORT ORD REUSE AUTHORITY TO FUND ASSISTANCE WITH AQUIFER STORAGE AND RECOVERY
SITE EXPANSION |
||||
|
|||||
Meeting Date: |
March 17, 2014 |
Budgeted: |
Yes |
||
|
|||||
From: |
David J. Stoldt, |
Program/ |
Water Supply |
||
|
General Manager |
Line Item No.: |
1-2-1 B. 1 |
||
|
|||||
Prepared By: |
Joe Oliver |
Cost Estimate: |
$24,000 |
||
|
|||||
General Counsel Review: pending |
|||||
Committee Recommendation: The Administrative Committee considered
this item on March 10, 2014 and recommended approval. |
|||||
CEQA Compliance: N/A |
|||||
SUMMARY: The Board will consider approval
of a reimbursement agreement between the Monterey Peninsula Water Management
District (MPWMD or District) and the Fort Ord Reuse Authority (FORA) to enable expansion
of the Santa Margarita or Phase 1 Aquifer Storage and Recovery (ASR) site near
the intersection of General Jim Moore Boulevard and Eucalyptus Road in
Seaside. The draft FORA reimbursement
agreement is included as Exhibit 4-A.
The agreement will allow FORA staff and its contractors to process the
approvals needed for a minor site expansion to adjacent property under the
jurisdiction of FORA. The property
adjacent to the ASR site does not currently have all the necessary clearances
for Unexploded Ordnance (UXO) and FORA is required to carry out this work prior
to certain uses on the property. The
purpose for the expansion is to facilitate installation of permanent
underground pipelines to the ASR site Facility Building and allow for expansion
of the onsite backflush basin. In
addition, the site expansion space will be utilized for a vehicle driveway that
is needed for truck deliveries to the Facility Building.
RECOMMENDATION:
It is recommended that the Board authorize staff to finalize the FORA
reimbursement agreement for a not-to-exceed amount of $24,000. The General Manager will be authorized to
execute this agreement and proceed with payments to FORA for their work in
enabling the use of property adjacent to the Santa Margarita ASR site, if this
item is adopted.
BACKGROUND:
The MPWMD has been developing the Santa Margarita ASR site since 1999. The project transitioned from feasibility
testing to permanent operation status with issuance of SWRCB Amended Permit
20808A in December 2007, and the project has been operated jointly by MPWMD and
Cal-Am since then. To date (i.e., through
Water Year 2013), approximately 4,770 acre-feet (AF) of water have been
diverted from Cal-Am’s Carmel River production sources for injection into the
Seaside Groundwater Basin. Of this
amount, approximately 4,050 AF have been diverted for injection at the Santa
Margarita ASR site. When the Santa
Margarita site was originally planned and developed by MPWMD, it was intended as
a “stand-alone” facility for two ASR wells and associated water treatment
facilities. However, through ongoing
discussions with Cal-Am and their technical consultants, the potential use of
the site has been expanded to include connection with other ASR facilities
under development or in the planning stages in the basin. The need for connection to these other
facilities has been heightened by the recent requirement to locate additional
backflush basin capacity at this site for the two ASR wells at the nearby
Seaside Middle School or Phase 2 ASR site.
Ultimately, it is now planned that the treatment capacity of the
Facility Building at the Santa Margarita ASR site will also be sized for future
planned operations contemplated as part of the ASR component of the Monterey
Peninsula Water Supply Project. These
requirements have necessitated that an additional small piece of adjacent property
be added to the site to accommodate these currently planned uses at the
site. Accordingly, MPWMD, FORA and the
City of Seaside have been working closely on the land use approvals needed to
acquire the additional strip of land.
The next step in this process is to enter into the reimbursement
agreement with FORA. Concurrently, MPWMD
is working with the City of Seaside to negotiate the terms for use of this
additional land and to secure a grading permit under their “Ordnance Ordinance”
to allow the excavation work for the ground disturbing work to proceed. The Board will be apprised of additional
requirements as this process moves forward in the coming months.
IMPACT TO STAFF/RESOURCES:
A significant staff effort has been expended in planning, coordinating,
analyzing and overseeing work on the District’s ASR testing program in the
Seaside Basin. This current item will be
a continuation of that effort. Funding
for this item is included in the District’s Fiscal Year 2013-14 budget.
EXHIBIT
4-A Draft “Agreement for Professional Services”
with FORA
U:\staff\Boardpacket\2014\20140317\ConsentClndr\04\item4.docx