WATER SUPPLY PLANNING COMMITTEE

 

ITEM:

PROGRESS REPORTS

 

5.

ACTIVITY RELATED TO WATER PROJECTS 1  (AQUIFER STORAGE & RECOVERY (“ASR”)) AND 2 (EXPANDED ASR)

 

Meeting Date:

November 22, 2011

Budgeted: 

 N/A

 

From:

David J. Stoldt,

Program/

N/A

 

General Manager

Line Item No.:

 

Prepared By:

David J. Stoldt

Cost Estimate:

N/A

 

General Counsel Review:  N/A

Committee Recommendation: N/A

CEQA Compliance:  N/A

 

SUMMARY:  An implementation plan and timeline for Water Project 2 is attached as Exhibit 5-A.

 

EXHIBITS

5-A      Eater Project 2 Implementation Plan and Timeline

 

 

 

 

 