WATER SUPPLY PLANNING COMMITTEE

 

ITEM:

ACTION ITEM

 

3.

DEVELOP RECOMMENDATION TO THE BOARD ON GROUNDWATER REPLENISHMENT CRITERIA FOR THE GO/NO-GO DECISION

 

Meeting Date:

May 2, 2013

Budgeted: 

N/A

 

From:

David J. Stoldt

Program/

 

 

General Manager

Line Item No.:     

 

Prepared By:

David J. Stoldt

Cost Estimate:

 

 

General Counsel Approval:  N/A

Committee Recommendation:  N/A

CEQA Compliance:  N/A

 

SUMMARY:  On June 12, 2013 the California Public Utilities Commission (CPUC) will hold a workshop in on criteria for including the Groundwater Replenishment project (GWR) in the mix of water supply solutions under A. 12-04-019.  The workshop is being held because the Division of Ratepayer Advocate’s February 2013 direct testimony requested it; the Planning and Conservation League Foundation’s December 2012 motion requested such; The Governance Committee’s March 2013 letter requested such; and the April 2012 3-Party MOU envisioned development of criteria.  The GWR “go/no go” decision receives “Category A” treatment under the MPWSP Governance Committee agreement meaning it is to be made by the public agency members, however the CPUC will likely attempt to define criteria in its Decision.  Therefore it is important that the public agencies bring criteria into the workshop reflective of our desires.

 

The criteria attached reflect comments received from the Monterey Peninsula Regional Water Authority Technical Advisory Committee and the Monterey Peninsula Water Supply Project Governance Committee.

 

RECOMMENDATION:  The Committee should discuss whether to recommend that the Board approve the attached criteria for the GWR “Go/No-Go” decision for submittal at the June 12 CPUC Workshops.

 

EXHIBIT

3-A      Proposed GWR “Go/No-Go” Criteria

 

 

 

 

 

 

 

U:\staff\Board_Committees\WSP\2013\20130502\03\item3.docx