ITEM:

PUBLIC HEARING

 

18.

CONSIDER ADOPTION OF MID-YEAR FISCAL YEAR 2015-2016 BUDGET ADJUSTMENT

 

Meeting Date:

February 17, 2016

Budgeted: 

N/A

 

From:

David J. Stoldt,

Program/

N/A

 

General Manager

Line Item No.:

 

Prepared By:

Suresh Prasad

Cost Estimate:

N/A

 

General Counsel Review:  N/A

Committee Recommendation:  N/A

CEQA Compliance:  N/A

 

SUMMARY:  Annually, the District considers its financial position after the end of the first half of the fiscal year (FY).  District staff has reviewed income and spending patterns since July 1, 2015 through the end of December 31, 2015 and determined that adjustments to the FY 2015-2016 Budget is required.  The FY 2015-2016 Budget was adopted on June 15, 2015.  Included in the budget adjustment process was a review of staffing levels, supplies, outside services, current work assignments and other factors affecting the current budget.  The table below summarizes the proposed changes to the budget:

 

Monterey Peninsula Water Management District

2015-2016 Budget

Mid-Year Budget Adjustment-Summary

Revenue

Adopted

Change

Amended

Property Tax

$1,570,000

$0

$1,570,000

Permit Fees - WDD

175,000

0

175,000

Permit Fees - PED

56,000

0

56,000

Connection Charges

175,000

0

175,000

User Fees

75,000

0

75,000

Water Supply Charge

3,400,000

0

3,400,000

Mitigation Revenue

2,412,000

0

2,412,000

Recording Fees

8,000

0

8,000

Interest

15,000

0

15,000

Other

15,000

0

15,000

Subtotal District Revenues

7,901,000

0

7,901,000

Reimbursements - CAW

1,841,900

(594,100)

1,247,800

Reimbursements - Watermaster

70,200

0

70,200

Reimbursements - Other

67,000

(11,000)

56,000

Reimbursements - Legal Fees

15,000

0

15,000

Grants

275,000

0

275,000

Subtotal Reimbursements

$2,269,100

($605,100)

$1,664,000

 

 

 

 

 

 

 

 

Carry Forward From Prior Year

1,220,000

0

1,220,000

From Capital Equipment Reserve

0

89,700

89,700

From Fund Balance

2,021,400

1,034,750

3,056,150

Total Revenues

$13,411,500

$519,350

$13,930,850

Expenditures

Adopted

Change

Amended

Personnel

$3,405,000

$39,300

$3,444,300

Supplies & Services

1,074,100

0

1,074,100

Project Expenditures

7,900,300

484,800

8,385,100

Fixed Assets

144,500

29,700

174,200

General Operating Reserve

354,600

133,550

488,150

Debt Service

230,000

0

230,000

Election Expense

228,000

(168,000)

60,000

Contingency

75,000

0

75,000

       Total

$13,411,500

$519,350

$13,930,850

 

As the revenue and expenditure tables indicate, revenue and expenditure increases by $519,350 resulting in a balanced budget.  In order to balance the budget and fund for continuing work on the Ground Water Replenishment Project, additional funding in the amount of $1,034,750 will have to be borrowed from District’s general reserve fund to complete the project.  Detailed information regarding the proposed changes, as well as their effect on reserves, is detailed in the background section of this report.

 

RECOMMENDATION:  Following a presentation by District staff and a public hearing, staff recommends adoption of the proposed mid-year budget adjustment for FY 2015-2016.

 

BACKGROUND:  The Board of Directors adopted the original FY 2015-2016 budget on June 15, 2015.  The paragraphs below summarize the original budget, proposed mid-year adjustments to the budget and projected reserves accounts.

 

Revenues

 

The 2015-2016 adopted budget anticipated revenue sources in the amount of $13,411,500.  It was projected that these revenues would be the same amount as budgeted expenditures resulting in a balanced budget.  As of December 31, 2015, actual revenue collections totaled $4,061,842 or about 30% of the budgeted amount.  Revenues for the first half of each FY year are low because one half of the District’s three major revenue sources, water supply charge, property taxes and reimbursements, are collected during the second half of each FY.  District staff has analyzed the revenue activity for the first six months of the FY, as well as activities scheduled for the second half of the FY, and recommends various adjustments to the revenue portion of the budget as shown in Exhibit 18-A and discussed below:

 

 

 

 

 

The cumulative effect of these revenue adjustments is an increase of $519,350 in projected revenues for FY 2015-2016.

 

Expenditures

 

The original budget envisioned expenditures of $13,411,500 in the FY ending June 30, 2016. As of December 31, 2015, actual expenditures totaled $4,068,924, or approximately 30% of the budgeted amount.  This low percentage at the mid-way point of the FY is not unusual because project expenditures for the first half of each FY year are historically low.  District staff has analyzed the expenditure activity for the first six months of the FY, as well as activities scheduled for the second half of the FY, and recommends various adjustments to the expenditure portion of the budget as discussed below:

 

 

 

 

 

The cumulative effect of the adjustments to the expenditure side of the budget is a net increase of $484,800 in projected expenditures for FY 2015-2016.  

 

Reserves

 

The District’s reserve balance is projected to be as follows:

 

 

The above adjustments will result in an estimated reserve balance of 2,190,185 at June 30, 2016 as shown on Exhibit 18-F.  This amount meets the minimum 5% of the operating budget established by the Board during the 2005-06 budget process.

 

EXHIBITS

18-A    Revenues

18-B    Personnel Costs

18-C    Supplies & Services Costs

18-D    Capital Assets

18-E    Project Expenditures

18-F    Reserves Analysis

 

 

U:\staff\Boardpacket\2016\20160217\PubHrngs\18\Item-18.docx